2180 S WESTWOOD BLVD 90025
Certificate Information: 2180 S WESTWOOD BLVD 90025
- Application / Permit
- 21016-10000-21170
- Plan Check / Job No.
- B21LA15167
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (15) Telecommunication Transmitter - wireless
- Work Description
- ePlan Check* Modify existing wireless facility -Remove and repalce exsting antennas -Remove and replace RRUs -Remove and replace powerplant and batteries -Install additional battery rack and batteries
- Permit Issued
- Issued on 11/10/2021
- Issuing Office
- Current Status
- Permit Finaled on 9/24/2024
Permit Application Status History
| Submitted | 8/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2021 | CELESTE MORRIS |
| Corrections Issued | 8/21/2021 | CELESTE MORRIS |
| Plan Check Approved | 10/22/2021 | CELESTE NGUYEN |
| Issued | 11/10/2021 | APPLICANT |
| Permit Finaled | 9/24/2024 | CASIMIR BRITTON |
Permit Application Clearance Information
| Supp. Use District POD/CDO/TDO | Cleared | 9/20/2021 | DYLAN SITTIG |
| Plan Approval | Cleared | 10/15/2021 | DANG NGUYEN |
| ZA Case | Cleared | 10/15/2021 | DANG NGUYEN |
| ZA Case | Cleared | 10/15/2021 | DANG NGUYEN |
| ZA Case | Cleared | 10/15/2021 | DANG NGUYEN |
Contact Information
| Contractor | Bechtel Infrastructure And Power Corporation; Lic. No.: 913045-B | 5323 N 99TH AVENUE C/O T OLSON GLENDALE, AZ 85305 |
| Engineer | Lee,, Chris S; Lic. No.: C76549 | 400 S NORTON AVE A LOS ANGELES, CA 90020 |
| Engineer | Lee,, Chris S; Lic. No.: NA76549 | , |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| SGSOV-Seismic Gas S/O Valve | 9/4/2024 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 9/4/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 9/6/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Not Ready | CASIMIR BRITTON |
| Smoke Detectors | 9/6/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| Final | 9/24/2024 | Permit Finaled | CASIMIR BRITTON |
| SGSOV-Seismic Gas S/O Valve | 9/24/2024 | SGSOV Approved | CASIMIR BRITTON |
| Smoke Detectors | 9/24/2024 | Approved | CASIMIR BRITTON |