100 N ROBERTSON BLVD 90048
Certificate Information: 100 N ROBERTSON BLVD 90048
- Application / Permit
- 21016-10000-21143
- Plan Check / Job No.
- B21LA15141
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- TENANT IMPROVEMENT IN EXISTING GROUND FLOOR RETAIL SPACE. PROJECT INCLUDES NEW NON-STRUCTURAL PARTITIONS, FIXTURES, AND FINISHES. RECONFIGURING EXISTING RESTROOM TO BE ADA COMPLIANT. INSTALL NEW EXIT DOOR AND REAR ENTRY DOORS FROM PARKING LOT AND PROVIDE NEW RAISED SIDEWALK AND WHEELCHAIR RAMP. RE-STRIPE PARKING STALLS AT NEW LOCATION TO MAKE ROOM FOR WHEELCHAIR RAMP AND SIDEWALK.
- Permit Issued
- Issued on 11/17/2021
- Issuing Office
- Current Status
- Permit Finaled on 5/23/2022
Permit Application Status History
| Submitted | 8/12/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 8/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | SERGIO GUTIERREZ |
| Corrections Issued | 9/22/2021 | SERGIO GUTIERREZ |
| Quality Review Completed | 9/27/2021 | FARUK SEZER |
| Plan Check Approved | 11/4/2021 | SERGIO GUTIERREZ |
| Issued | 11/17/2021 | APPLICANT |
| Building Plans Picked Up | 11/19/2021 | APPLICANT |
| Permit Finaled | 5/23/2022 | KATY RAMIREZ |
Permit Application Clearance Information
| "Q" conditions | Cleared | 10/5/2021 | PABLO ESTRADA |
| DAS Clearance | Cleared | 10/20/2021 | SHINE LIN |
Contact Information
| Architect | , ; Lic. No.: C38522 | , |
| Contractor | Slater Construction And Development Inc; Lic. No.: 339608-B | 200 S BARRINGTON AVE 1486 LOS ANGELES, CA 90049 |
| Engineer | Lobnan,, Essam; Lic. No.: C78053 | PO BOX 64373 LOS ANGELES, CA 90064 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/22/2021 | Approved | JONATHAN QUACH |
| Light Gage Steel Frame | 12/22/2021 | Partial Approval | JONATHAN QUACH |
| Drywall Nailing | 12/30/2021 | Approved | JONATHAN QUACH |
| Special/Order Compliance | 5/9/2022 | Partial Inspection | KATY RAMIREZ |
| Final | 5/23/2022 | Permit Finaled | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 5/23/2022 | SGSOV Approved | KATY RAMIREZ |
| Smoke Detectors | 5/23/2022 | Approved | KATY RAMIREZ |