6804 S HAAS AVE 90047

Certificate Information: 6804 S HAAS AVE 90047

Application / Permit
21016-10000-21092
Plan Check / Job No.
B21LA15094
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ENLARAGE & CONVERT (E) DETACHED GARAGE INTO ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 10/26/2021
Issuing Office
Current Status
CofO Issued on 2/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2021 APPLICANT
Assigned to Plan Check Engineer 8/17/2021 RICARDO RAMIREZ
Corrections Issued 8/17/2021 RICARDO RAMIREZ
Applicant returned to address corrections 9/22/2021 TSE MING HUANG
Applicant returned to address corrections 10/18/2021 RICARDO RAMIREZ
Plan Check Approved 10/19/2021 RICARDO RAMIREZ
Issued 10/26/2021 APPLICANT
Building Plans Picked Up 10/27/2021 APPLICANT
CofO in Progress 2/10/2025 BARRY HACHE
Permit Finaled 2/23/2025 DEROLD HAUFF
CofO Issued 2/23/2025 DEROLD HAUFF
Permit Finaled 2/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/25/2021 CELINA MORENO
Roof/Waste drainage to street Cleared 8/25/2021 CELINA MORENO
Sewer availability Cleared 8/25/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 9/10/2021 CELINA MORENO
Construction near power lines Cleared 10/16/2021 RIDWAN HARDY
Construction within easement Cleared 10/16/2021 RIDWAN HARDY

Contact Information

Contractor Valencia Construction Company; Lic. No.: 1015167-B 12069 SMALLWOOD AVE      DOWNEY, CA 90242
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/20/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 1/20/2022 Partial Approval JOAQUIN GREENOUGH
Rough-Elec/Plmb/HVAC 2/15/2022 Approved HORACE FULTZ
Wood Frame 2/15/2022 Approved HORACE FULTZ
Insulation 3/7/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 3/7/2022 Partial Inspection FREDDIE RIVERA
Drywall Nailing 3/16/2022 Approved ENRIQUE MIRELES
Shower Pan 4/7/2022 Approved ENRIQUE MIRELES
Sewer 5/2/2022 Corrections Issued ENRIQUE MIRELES
Underground Mechanical 5/6/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 5/11/2022 Approved ENRIQUE MIRELES
Sewer 5/11/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 7/22/2022 Approved ENRIQUE MIRELES
Final 7/22/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 7/22/2022 Approved ENRIQUE MIRELES
Green Building Rough 7/22/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 7/22/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 7/22/2022 Approved ENRIQUE MIRELES
Final 7/28/2022 Not Ready for Inspection SABAS ALONSO
Final 2/6/2025 OK to Issue CofO BARRY HACHE