3576 N DOVER ST 90039
Certificate Information: 3576 N DOVER ST 90039
- Application / Permit
- 21016-10000-21076
- Plan Check / Job No.
- B21LA15082
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE TO ADU PER STATE ORDINANCE # 186481.
- Permit Issued
- Issued on 5/20/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2021 | TSE MING HUANG |
| Corrections Issued | 8/17/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 3/1/2022 | ZAW HAN |
| Applicant returned to address corrections | 4/6/2022 | TSE MING HUANG |
| Building Plans Picked Up | 5/4/2022 | APPLICANT |
| Plan Check Approved | 5/10/2022 | JOSEPH RAFOLS |
| Issued | 5/20/2022 | APPLICANT |
| CofO in Progress | 7/18/2024 | COREY HUPP |
| CofO Issued | 8/6/2024 | DANIEL SANCHEZ |
| Permit Finaled | 8/6/2024 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/4/2022 | CELINA MORENO |
| ZI | Cleared | 3/7/2022 | JASON CHAN |
| Construction near power lines | Cleared | 3/8/2022 | TINA MIRANDA |
| Construction within easement | Cleared | 3/8/2022 | TINA MIRANDA |
| Address approval | Cleared | 3/15/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2022 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/26/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Rough-Elec/Plmb/HVAC | 5/31/2022 | Partial Inspection | ALFREDO BALANDRA |
| Wood Frame | 5/31/2022 | Partial Inspection | ALFREDO BALANDRA |
| Footing/Foundation/Slab | 6/23/2022 | Approved | COREY HUPP |
| PLUMBING-Rough | 6/23/2022 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 6/27/2022 | Partial Inspection | ROBERT MINASSIANS |
| Footing/Foundation/Slab | 6/27/2022 | Corrections Issued | ROBERT MINASSIANS |
| Rough-Elec/Plmb/HVAC | 6/27/2022 | Partial Inspection | ROBERT MINASSIANS |
| ELECTRICAL-Rough | 10/10/2023 | Approved | COREY HUPP |
| Rough-Elec/Plmb/HVAC | 10/31/2023 | Approved | COREY HUPP |
| Drywall Nailing | 11/6/2023 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 7/17/2024 | Approved | COREY HUPP |
| Final | 7/17/2024 | OK to Issue CofO | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 7/17/2024 | SGSOV Approved | COREY HUPP |
| Smoke Detectors | 7/17/2024 | Approved | COREY HUPP |