347 1/2 N CROFT AVE 90048

Certificate Information: 347 1/2 N CROFT AVE 90048

Application / Permit
21016-10000-21068
Plan Check / Job No.
B21LA15078
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Demolition partition of (E) garage and convert to ADU per State Law.
Permit Issued
Issued on 7/8/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2021 APPLICANT
Assigned to Plan Check Engineer 8/17/2021 TSE MING HUANG
Corrections Issued 8/17/2021 TSE MING HUANG
Applicant returned to address corrections 3/10/2022 TSE MING HUANG
Applicant returned to address corrections 4/5/2022 TSE MING HUANG
Plan Check Approved 4/11/2022 TSE MING HUANG
Building Plans Picked Up 5/10/2022 APPLICANT
Issued 7/8/2022 APPLICANT
CofO in Progress 4/5/2023 MICHAEL LEWIS
Permit Finaled 4/7/2023 DEROLD HAUFF
CofO Issued 4/7/2023 DEROLD HAUFF
Permit Finaled 4/7/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/30/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 8/30/2021 RENZ SORIANO
Sewer availability Cleared 8/30/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 9/1/2021 RENZ SORIANO
Construction near power lines Cleared 11/24/2021 RIDWAN HARDY
Construction within easement Cleared 11/24/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 866      HAWTHORNE, CA 90251

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/5/2022 Corrections Issued MICHAEL LEWIS
Underground Mechanical 12/5/2022 Approved MICHAEL LEWIS
Footing/Foundation/Slab 12/8/2022 Approved MICHAEL LEWIS
ELECTRICAL-Rough 1/6/2023 Approved MICHAEL LEWIS
HVAC-Rough 1/6/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 1/6/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 1/18/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 1/18/2023 Approved MICHAEL LEWIS
Insulation 1/18/2023 Partial Approval MICHAEL LEWIS
Insulation 1/24/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 1/24/2023 Approved MICHAEL LEWIS
Underground Mechanical 1/24/2023 Approved MICHAEL LEWIS
Drywall Nailing 2/1/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 2/1/2023 Approved MICHAEL LEWIS
Shower Pan 2/1/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 3/28/2023 Approved MICHAEL LEWIS
Final 3/28/2023 Corrections Issued MICHAEL LEWIS
MERV13>=Final 3/28/2023 Approved MICHAEL LEWIS
METHANE-Final 3/28/2023 Approved MICHAEL LEWIS
METHANE-Rough 3/28/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 3/28/2023 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 3/28/2023 Approved MICHAEL LEWIS
Final 4/4/2023 OK to Issue CofO MICHAEL LEWIS