152 S VISTA ST 90036
Certificate Information: 152 S VISTA ST 90036
- Application / Permit
- 21016-10000-21052
- Plan Check / Job No.
- B21LA15051
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT PORTION OF (E) GARAGE TO AN ADU
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- CofO Issued on 12/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2021 | TSE MING HUANG |
| Corrections Issued | 8/19/2021 | TSE MING HUANG |
| Building Plans Picked Up | 8/27/2021 | APPLICANT |
| Applicant returned to address corrections | 11/17/2021 | ZAW HAN |
| Plan Check Approved | 12/6/2021 | FERNANDO FLORES |
| Issued | 3/2/2022 | APPLICANT |
| CofO in Progress | 11/28/2022 | MICHAEL LEWIS |
| Permit Finaled | 12/10/2022 | DEROLD HAUFF |
| CofO Issued | 12/10/2022 | DEROLD HAUFF |
| Permit Finaled | 12/10/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/2/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 10/2/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 10/4/2021 | RENZ SORIANO |
| CPC | Cleared | 11/29/2021 | DANIEL MATA |
| CPC | Cleared | 11/29/2021 | DANIEL MATA |
| HPOZ | Cleared | 11/29/2021 | DANIEL MATA |
Contact Information
| Architect | Johnson,, David Michael; Lic. No.: C18045 | 3638 AUREOLA BLVD LOS ANGELES, CA 90008 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/1/2022 | Approved | ADAM ESCOTO |
| Footing/Foundation/Slab | 4/5/2022 | Approved | ADAM ESCOTO |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2022 | Partial Approval | ADAM ESCOTO |
| Green Building Rough | 4/22/2022 | Not Ready for Inspection | ADAM ESCOTO |
| METHANE-Rough | 4/22/2022 | Approved | ADAM ESCOTO |
| BUILDING-Rough-Frame | 5/4/2022 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 5/4/2022 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 5/4/2022 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/4/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 5/24/2022 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2022 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/6/2022 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 6/14/2022 | Approved | ADAM ESCOTO |
| Green Building Rough | 6/14/2022 | Approved | ADAM ESCOTO |
| HVAC-Rough | 6/14/2022 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 6/14/2022 | Approved | ADAM ESCOTO |
| BUILDING-Rough-Frame | 10/11/2022 | Approved | MICHAEL LEWIS |
| Final | 10/11/2022 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 10/11/2022 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 10/11/2022 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 10/11/2022 | Approved | MICHAEL LEWIS |
| Final | 11/10/2022 | Conditional Approval | MICHAEL LEWIS |
| Green Building Final | 11/10/2022 | Approved | MICHAEL LEWIS |
| Final | 11/28/2022 | OK to Issue CofO | MICHAEL LEWIS |