980 W 190TH ST B-4 90502

Certificate Information: 980 W 190TH ST B-4 90502

Application / Permit
21016-10000-20843
Plan Check / Job No.
B21LA14932
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
INTERIOR NON-STRUCTURAL TENANT IMPROVEMENT WORK. CHANGE OF USE FROM RETAIL TO RESTAURANT. NO EXTERIOR WORK. AREA OF SUITE AND WORK.
Permit Issued
Issued on 1/11/2022
Issuing Office
Current Status
CofO Issued on 6/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/11/2021 APPLICANT
Disabled Access Plans Picked Up 8/30/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 FARSHAD ALIMOHAMADI
Corrections Issued 9/9/2021 FARSHAD ALIMOHAMADI
Quality Review Completed 9/9/2021 SAI KHUM
Applicant returned to address corrections 11/30/2021 FARSHAD ALIMOHAMADI
Plan Check Approved 12/17/2021 FARSHAD ALIMOHAMADI
Issued 1/11/2022 APPLICANT
Building Plans Picked Up 1/14/2022 APPLICANT
CofO in Progress 6/14/2023 JOEY BUCHANAN
Permit Finaled 6/14/2023 DAVID TSAU
CofO Issued 6/14/2023 DAVID TSAU
Permit Finaled 6/14/2023 DAVID TSAU

Permit Application Clearance Information

Miscellaneous Cleared 9/13/2021 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 9/21/2021 CHINH DINH
Sewer availability Cleared 9/21/2021 CHINH DINH
DAS Clearance Cleared 10/14/2021 FARSHAD ALIMOHAMADI
Food establishment approval Cleared 10/26/2021 LACDHS APPROVED
Food Service Establishment Cleared 12/15/2021 JASH PATEL

Contact Information

Architect Barany,, Donald Alec; Lic. No.: C12803 116 26TH ST      SANTA MONICA, CA 90402
Contractor Gaudenti & Sons Corporation; Lic. No.: 283650-B 231 VISTA DEL MAR      REDONDO BEACH, CA 90277
Engineer Roth,, Jennifer Nicole; Lic. No.: C84889 110 THE VILLAGE UNIT 504      REDONDO BEACH, CA 90277

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/3/2022 Not Ready for Inspection JOEY BUCHANAN
Deputy Drilled-In Anchors 2/7/2022 Approved JOEY BUCHANAN
Final 4/28/2023 Not Ready for Inspection JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 4/28/2023 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 4/28/2023 Approved JOEY BUCHANAN
Wood Frame 4/28/2023 Approved JOEY BUCHANAN
Drywall Nailing 6/12/2023 Approved JOEY BUCHANAN
Final 6/12/2023 Conditional Approval JOEY BUCHANAN
T-Bar Ceiling 6/12/2023 Approved JOEY BUCHANAN