2328 S CAMDEN AVE 90064
Certificate Information: 2328 S CAMDEN AVE 90064
- Application / Permit
- 21016-10000-20679
- Plan Check / Job No.
- B21LA14810
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERT (E) DETACHED GARAGE WITH NEW ADDITION INTO AN ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 5/6/2022
- Issuing Office
- Current Status
- CofO Issued on 9/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2021 | KEVIN MORALES |
| Corrections Issued | 8/18/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 9/20/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 3/15/2022 | KEVIN MORALES |
| Plan Check Approved | 3/22/2022 | KEVIN MORALES |
| Issued | 5/6/2022 | APPLICANT |
| CofO in Progress | 9/15/2023 | JESUS PINEDA |
| Permit Finaled | 9/21/2023 | DANIEL ORRANTE |
| CofO Issued | 9/21/2023 | DANIEL ORRANTE |
| Permit Finaled | 9/21/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/19/2021 | DINAH GARIN |
| Sewer availability | Cleared | 8/19/2021 | DINAH GARIN |
| Specific Plan | Cleared | 10/26/2021 | DYLAN SITTIG |
| Specific Plan | Cleared | 10/28/2021 | KEVIN ARUCAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2022 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tran,, Duane Phat; Lic. No.: C91229 | 1106 S NEWHOPE ST SANTA ANA, CA 92704 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/21/2022 | Conditional Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 12/21/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/10/2023 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 1/11/2023 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 2/9/2023 | Corrections Issued | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2023 | Partial Approval | CLAYTON GRAHAM |
| Green Building Rough | 2/9/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| HVAC-Rough | 2/9/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 2/9/2023 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 3/3/2023 | Approved | JOHNNY MIRANDA |
| Insulation | 3/3/2023 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2023 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 3/15/2023 | Conditional Approval | JOHNNY MIRANDA |
| Green Building Rough | 3/15/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 3/15/2023 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 5/2/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 5/2/2023 | Approved | JOHNNY MIRANDA |
| Sewer | 5/2/2023 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 6/2/2023 | Approved | JOHNNY MIRANDA |
| Final | 6/2/2023 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 6/2/2023 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 6/2/2023 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 6/2/2023 | Approved | JOHNNY MIRANDA |
| Final | 6/15/2023 | Corrections Issued | JOHNNY MIRANDA |
| Final | 9/15/2023 | OK to Issue CofO | JESUS PINEDA |