1607 1/2 W 48TH ST 90062

Certificate Information: 1607 1/2 W 48TH ST 90062

Application / Permit
21016-10000-20561
Plan Check / Job No.
B21LA14735
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING DETACHED GARAGE CONVERSION TO 645 SF ADU PER GCS 65852.2(e)(1)(A).ALL WORK PER ENGINEER DESIGN.
Permit Issued
Issued on 11/4/2021
Issuing Office
Current Status
CofO Issued on 11/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2021 APPLICANT
Assigned to Plan Check Engineer 8/11/2021 ZAW HAN
Corrections Issued 8/17/2021 ZAW HAN
Applicant returned to address corrections 10/28/2021 ZAW HAN
Plan Check Approved 11/1/2021 ZAW HAN
Issued 11/4/2021 APPLICANT
Building Plans Picked Up 11/9/2021 APPLICANT
CofO in Progress 11/9/2023 CRAIG DAVIS
Permit Finaled 11/26/2023 DEROLD HAUFF
CofO Issued 11/26/2023 DEROLD HAUFF
Permit Finaled 11/26/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/21/2021 RENZ SORIANO
Highway dedication Cleared 8/21/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 8/21/2021 RENZ SORIANO
Sewer availability Cleared 8/21/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 8/23/2021 RENZ SORIANO
Tenant Habitability Plan Cleared 9/24/2021 MICHAEL SOTO

Contact Information

Contractor Jerahian Araz; Lic. No.: 1045340-B 250 N COLLEGE PARK DR F36      UPLAND, CA 91786
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/19/2023 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 3/8/2023 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 5/8/2023 Corrections Issued LILIANA PORTILLO
HVAC-Rough 5/8/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 5/8/2023 Approved LILIANA PORTILLO
Sewer 5/8/2023 Approved LILIANA PORTILLO
Underground Mechanical 5/8/2023 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 5/15/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 5/15/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/15/2023 Partial Approval SABAS ALONSO
Green Building Rough 5/15/2023 Approved SABAS ALONSO
Underground Mechanical 5/15/2023 Partial Approval SABAS ALONSO
Insulation 5/24/2023 Approved JOAQUIN GREENOUGH
Drywall Nailing 6/1/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 6/1/2023 Approved STUART CHAPMAN
Underground Mechanical 8/29/2023 Partial Approval SABAS ALONSO
Final 9/15/2023 Corrections Issued SABAS ALONSO
Gas Test 9/15/2023 Approved SABAS ALONSO
Green Building Final 9/15/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/15/2023 SGSOV Approved SABAS ALONSO
Smoke Detectors 9/15/2023 Approved SABAS ALONSO
Final 9/25/2023 Corrections Issued SABAS ALONSO
Final 10/25/2023 Not Ready for Inspection RONNIE MINDANAO
Final 10/27/2023 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 11/6/2023 Approved CRAIG DAVIS
Final 11/6/2023 Partial Approval CRAIG DAVIS
Final 11/8/2023 OK to Issue CofO CRAIG DAVIS
Service/Power Release 11/8/2023 Approved CRAIG DAVIS