3743 S HILLCREST DR 90016

Certificate Information: 3743 S HILLCREST DR 90016

Application / Permit
21016-10000-20361
Plan Check / Job No.
B21LA14635
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ADU PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 2/8/2022
Issuing Office
Current Status
CofO Issued on 6/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2021 APPLICANT
Assigned to Plan Check Engineer 8/9/2021 JOSEPH RAFOLS
Corrections Issued 8/9/2021 JOSEPH RAFOLS
Applicant returned to address corrections 8/25/2021 RICARDO RAMIREZ
Plan Check Approved 11/24/2021 DANIEL SANJUAN
Building Plans Picked Up 11/29/2021 APPLICANT
Issued 2/8/2022 APPLICANT
CofO in Progress 5/31/2023 STUART CHAPMAN
Permit Finaled 6/3/2023 DEROLD HAUFF
CofO Issued 6/3/2023 DEROLD HAUFF
Permit Finaled 6/3/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/17/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 8/17/2021 RENZ SORIANO
Sewer availability Cleared 8/17/2021 RENZ SORIANO
Construction near power lines Cleared 11/13/2021 RIDWAN HARDY

Contact Information

Contractor State Wide Construction & Remodeling Inc; Lic. No.: 830833-B 5632 VAN NUYS BLVD STE 1265      SHERMAN OAKS, CA 91401
Engineer Pineda,, Salvador Antonio; Lic. No.: S5233 PO BOX 7313      ALHAMBRA, CA 91802

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/23/2022 Corrections Issued ANTHONY EGSON
Underground Mechanical 3/8/2022 Approved HORACE FULTZ
Footing/Foundation/Slab 3/21/2022 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 4/21/2022 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/23/2022 Partial Approval ANTHONY EGSON
ELECTRICAL-Rough 8/15/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Approved ANTHONY EGSON
PLUMBING-Rough 8/15/2022 Approved ANTHONY EGSON
Insulation 8/26/2022 Partial Approval ANTHONY EGSON
Interior/Exterior Lathing 8/26/2022 Corrections Issued ANTHONY EGSON
Insulation 9/6/2022 Approved ANTHONY EGSON
Drywall Nailing 9/21/2022 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 9/21/2022 Partial Approval ANTHONY EGSON
Shower Pan 9/21/2022 Approved ANTHONY EGSON
Drywall Nailing 10/7/2022 Approved ANTHONY EGSON
HVAC-Rough 10/7/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 2/6/2023 Approved STUART CHAPMAN
Final 2/6/2023 Corrections Issued STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 2/6/2023 SGSOV Approved STUART CHAPMAN
Smoke Detectors 2/6/2023 Approved STUART CHAPMAN
Final 2/16/2023 Corrections Issued STUART CHAPMAN
ELECTRICAL-Final 5/31/2023 Approved STUART CHAPMAN
Final 5/31/2023 OK to Issue CofO STUART CHAPMAN
HVAC-Final 5/31/2023 Approved STUART CHAPMAN
PLUMBING-Final 5/31/2023 Approved STUART CHAPMAN