1009 N AVENUE 54 90042

Certificate Information: 1009 N AVENUE 54 90042

Application / Permit
21016-10000-20333
Plan Check / Job No.
B21LA14625
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
Convert (E) Garage and Rec-Room to ADU per LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 1/28/2022
Issuing Office
Current Status
CofO Issued on 11/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2021 APPLICANT
Assigned to Plan Check Engineer 8/9/2021 HERNAN ARREOLA
Corrections Issued 8/10/2021 HERNAN ARREOLA
Applicant returned to address corrections 1/10/2022 EDWIN ESPIN
Applicant returned to address corrections 1/11/2022 EDWIN ESPIN
Building Plans Picked Up 1/12/2022 APPLICANT
Plan Check Approved 1/25/2022 KHUONG TRUONG
Issued 1/28/2022 APPLICANT
CofO in Progress 10/25/2022 CRAIG VAUGHAN
CofO in Progress 10/25/2022 CRAIG VAUGHAN
Permit Finaled 11/19/2022 DEROLD HAUFF
CofO Issued 11/19/2022 DEROLD HAUFF
Permit Finaled 11/19/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/22/2021 KHOUNG LE
Sewer availability Cleared 12/22/2021 KHOUNG LE
Eng Process Fee Ord 176,300 Cleared 12/23/2021 KHOUNG LE
Grading Pre-Inspection Cleared 1/18/2022 VASIL MIHALEV

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/8/2022 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 3/23/2022 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 3/23/2022 Partial Approval CRAIG VAUGHAN
HVAC-Rough 3/23/2022 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 3/23/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 4/6/2022 Approved AMY COLIN
Insulation 4/6/2022 Approved AMY COLIN
Interior/Exterior Lathing 4/6/2022 Partial Approval AMY COLIN
Drywall Nailing 4/12/2022 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 4/18/2022 Approved CRAIG VAUGHAN
Wood Frame 4/18/2022 Approved CRAIG VAUGHAN
Final 6/30/2022 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 6/30/2022 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 6/30/2022 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 7/29/2022 Corrections Issued CRAIG VAUGHAN
HVAC-Final 7/29/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 7/29/2022 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 7/29/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Final 8/10/2022 Approved CRAIG VAUGHAN
Final 8/10/2022 OK to Issue CofO CRAIG VAUGHAN
PLUMBING-Final 8/10/2022 Approved CRAIG VAUGHAN