1429 S WALGROVE AVE 90066

Certificate Information: 1429 S WALGROVE AVE 90066

Application / Permit
21016-10000-20332
Plan Check / Job No.
B21LA14623
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADU conversion of existing recreation room above garage. New bathroom, shower, and kitchenette.
Permit Issued
Issued on 10/12/2021
Issuing Office
Current Status
CofO Issued on 11/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2021 APPLICANT
Assigned to Plan Check Engineer 8/9/2021 JOE VO
Corrections Issued 8/10/2021 JOE VO
Plan Check Approved 8/27/2021 JOE VO
Issued 10/12/2021 APPLICANT
CofO in Progress 11/16/2022 DAVID FEILER
Permit Finaled 11/30/2022 DANIEL ORRANTE
CofO Issued 11/30/2022 DANIEL ORRANTE
Permit Finaled 11/30/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/25/2021 DINAH GARIN
Sewer availability Cleared 8/25/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 8/26/2021 DINAH GARIN

Contact Information

Contractor Seacrest Development Inc ; Lic. No.: 1036456-B 1601 N SEPULVEDA BLVD   SUITE 702    MANHATTAN BEACH, CA 90266

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 11/30/2021 Corrections Issued DAVID FEILER
Rough-Elec/Plmb/HVAC 11/30/2021 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 12/7/2021 Approved DAVID FEILER
ELECTRICAL-Rough 12/7/2021 Approved DAVID FEILER
HVAC-Rough 12/7/2021 Approved DAVID FEILER
Insulation 12/7/2021 Conditional Approval DAVID FEILER
PLUMBING-Rough 12/7/2021 Approved DAVID FEILER
Insulation 12/16/2021 Corrections Issued JOHN KAYON
Drywall Nailing 12/20/2021 Approved DAVID FEILER
Shower Pan 12/20/2021 Approved DAVID FEILER
Drywall Nailing 12/23/2021 Approved JOHN KAYON
ELECTRICAL-Final 10/20/2022 Corrections Issued DAVID FEILER
Final 10/20/2022 Corrections Issued DAVID FEILER
HVAC-Final 10/20/2022 Approved DAVID FEILER
PLUMBING-Final 10/20/2022 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 10/20/2022 SGSOV Approved DAVID FEILER
Smoke Detectors 10/20/2022 Approved DAVID FEILER
ELECTRICAL-Final 11/1/2022 Approved DAVID FEILER
Final 11/15/2022 OK to Issue CofO DAVID FEILER