20300 S VERMONT AVE 90502

Certificate Information: 20300 S VERMONT AVE 90502

Application / Permit
21016-10000-20207
Plan Check / Job No.
B21LA14541
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
CHANGE OF USE FROM OFFICE TO MEDICAL OFFICE ON FIRST FLOOR.
Permit Issued
Issued on 4/27/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2021 APPLICANT
Assigned to Plan Check Engineer 9/3/2021 AUNG SOE
Corrections Issued 9/8/2021 AUNG SOE
Quality Review Completed 9/9/2021 EUGENE BARBEAU
Building Plans Picked Up 9/13/2021 APPLICANT
Green Plans Picked Up 9/13/2021 APPLICANT
Disabled Access Plans Picked Up 9/21/2021 APPLICANT
Applicant returned to address corrections 3/14/2022 AUNG SOE
Plan Check Approved 3/15/2022 AUNG SOE
Issued 4/27/2022 APPLICANT
CofO in Progress 1/13/2023 JOEY BUCHANAN
CofO Issued 1/19/2023 DAVID TSAU
Permit Finaled 1/19/2023 DAVID TSAU

Permit Application Clearance Information

Sewer availability Cleared 9/15/2021 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 9/17/2021 JOSE HERNANDEZ
Green Code Cleared 11/9/2021 AARON COSTA
DAS Clearance Cleared 3/3/2022 AUNG SOE

Contact Information

Architect Calvert,, Thomas Alan; Lic. No.: C14051 3829 LINDEN      LONG BEACH, CA 90807
Contractor Magnum Builders Inc; Lic. No.: 713775-B 25419 NARBONNE AVENUE      LOMITA, CA 907172125
Engineer Bushra,, Rafeek L; Lic. No.: S4490 2564 W WOODLAND DR      ANAHEIM, CA 92801

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/22/2022 Conditional Approval DAVID TSAU
Excavation/Setback/Form/Re-Bar 6/23/2022 Approved JOEY BUCHANAN
Insulation 7/7/2022 Approved JOEY BUCHANAN
Light Gage Steel Frame 7/7/2022 Partial Approval JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 7/20/2022 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 7/20/2022 Approved JOEY BUCHANAN
Reinforced Concrete Frame 7/20/2022 Approved JOEY BUCHANAN
Special/Order Compliance 7/20/2022 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 7/21/2022 Approved JOEY BUCHANAN
Light Gage Steel Frame 7/27/2022 Approved JOEY BUCHANAN
Smoke Detectors 7/27/2022 Approved JOEY BUCHANAN
Light Gage Steel Frame 8/15/2022 Approved JOEY BUCHANAN
T-Bar Ceiling 8/15/2022 Not Ready for Inspection JOEY BUCHANAN
Light Gage Steel Frame 8/31/2022 Approved JOEY BUCHANAN
T-Bar Ceiling 9/6/2022 Conditional Approval DARRYL ARNOLD
Light Gage Steel Frame 10/18/2022 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 11/8/2022 Approved JOEY BUCHANAN
Final 12/21/2022 Not Ready for Inspection JOEY BUCHANAN
Green Building Final 12/21/2022 Approved JOEY BUCHANAN
Green Building Rough 12/21/2022 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 12/21/2022 SGSOV Approved JOEY BUCHANAN
Wood Frame 12/21/2022 Approved JOEY BUCHANAN
Final 1/4/2023 Conditional Approval JOEY BUCHANAN