912 N AVENUE 57 90042

Certificate Information: 912 N AVENUE 57 90042

Application / Permit
21016-10000-19906
Plan Check / Job No.
B21LA14295
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU conversion. CONVERT EXISTING DETACHED GARAGE TO ADU PER PER GCS 65852.2(e)(1)(A) AND PER WFPP.
Permit Issued
Issued on 2/1/2022
Issuing Office
Current Status
CofO Issued on 8/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2021 APPLICANT
Assigned to Plan Check Engineer 8/4/2021 CRYSTEL MAALOUF
Corrections Issued 8/4/2021 CRYSTEL MAALOUF
Plan Check Approved 1/27/2022 CRYSTEL MAALOUF
Issued 2/1/2022 APPLICANT
CofO in Progress 8/10/2025 ALIZAH MAYAGOITIA
Permit Finaled 8/12/2025 DEROLD HAUFF
CofO Issued 8/12/2025 DEROLD HAUFF
Permit Finaled 8/12/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/16/2021 WALLIE JONG
Sewer availability Cleared 9/16/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/21/2021 WALLIE JONG
Grading Pre-Inspection Cleared 10/5/2021 BRIAN MILLER

Contact Information

Contractor All Construction Services; Lic. No.: 1056091-B 9018 BALBOA BLVD #509      NORTHRIDGE, CA 91325

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/4/2022 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 4/12/2022 Partial Approval CRAIG VAUGHAN
Underground Mechanical 4/12/2022 Partial Approval CRAIG VAUGHAN
Underground Mechanical 4/14/2022 No Access for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/18/2022 Partial Approval CRAIG VAUGHAN
Underground Mechanical 4/18/2022 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 4/22/2022 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 4/28/2022 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 5/2/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 5/20/2022 Partial Approval AMY COLIN
ELECTRICAL-Rough 5/20/2022 Corrections Issued AMY COLIN
PLUMBING-Rough 5/20/2022 Approved AMY COLIN
ELECTRICAL-Rough 5/24/2022 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 5/24/2022 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 5/27/2022 Approved CRAIG VAUGHAN
Green Building Rough 5/27/2022 Approved CRAIG VAUGHAN
Insulation 5/27/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 5/27/2022 Partial Approval CRAIG VAUGHAN
Drywall Nailing 6/7/2022 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 6/13/2022 Partial Approval KATHRYN BUTTERWORTH
Shower Pan 6/13/2022 Approved KATHRYN BUTTERWORTH
Final 9/13/2022 Corrections Issued SCOTT FINNILA
Green Building Final 9/13/2022 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 9/13/2022 SGSOV Not Ready SCOTT FINNILA
Smoke Detectors 9/13/2022 Approved SCOTT FINNILA
Final 9/22/2022 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 9/22/2022 SGSOV Approved CRAIG VAUGHAN
Final 11/4/2022 Corrections Issued CRAIG VAUGHAN
Final 2/18/2025 Not Ready for Inspection CRAIG DAVIS
Final 6/27/2025 Corrections Issued OSVALDO PARAMO
Final 8/11/2025 OK to Issue CofO ALIZAH MAYAGOITIA