912 N AVENUE 57 90042
Certificate Information: 912 N AVENUE 57 90042
- Application / Permit
- 21016-10000-19906
- Plan Check / Job No.
- B21LA14295
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADU conversion. CONVERT EXISTING DETACHED GARAGE TO ADU PER PER GCS 65852.2(e)(1)(A) AND PER WFPP.
- Permit Issued
- Issued on 2/1/2022
- Issuing Office
- Current Status
- CofO Issued on 8/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/31/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 8/4/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 1/27/2022 | CRYSTEL MAALOUF |
| Issued | 2/1/2022 | APPLICANT |
| CofO in Progress | 8/10/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 8/12/2025 | DEROLD HAUFF |
| CofO Issued | 8/12/2025 | DEROLD HAUFF |
| Permit Finaled | 8/12/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/16/2021 | WALLIE JONG |
| Sewer availability | Cleared | 9/16/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2021 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 10/5/2021 | BRIAN MILLER |
Contact Information
| Contractor | All Construction Services; Lic. No.: 1056091-B | 9018 BALBOA BLVD #509 NORTHRIDGE, CA 91325 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/4/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/12/2022 | Partial Approval | CRAIG VAUGHAN |
| Underground Mechanical | 4/12/2022 | Partial Approval | CRAIG VAUGHAN |
| Underground Mechanical | 4/14/2022 | No Access for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/18/2022 | Partial Approval | CRAIG VAUGHAN |
| Underground Mechanical | 4/18/2022 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/22/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 4/28/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 5/2/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/20/2022 | Partial Approval | AMY COLIN |
| ELECTRICAL-Rough | 5/20/2022 | Corrections Issued | AMY COLIN |
| PLUMBING-Rough | 5/20/2022 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 5/24/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 5/24/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/27/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 5/27/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 5/27/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 5/27/2022 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 6/7/2022 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 6/13/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Shower Pan | 6/13/2022 | Approved | KATHRYN BUTTERWORTH |
| Final | 9/13/2022 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 9/13/2022 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 9/13/2022 | SGSOV Not Ready | SCOTT FINNILA |
| Smoke Detectors | 9/13/2022 | Approved | SCOTT FINNILA |
| Final | 9/22/2022 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Final | 11/4/2022 | Corrections Issued | CRAIG VAUGHAN |
| Final | 2/18/2025 | Not Ready for Inspection | CRAIG DAVIS |
| Final | 6/27/2025 | Corrections Issued | OSVALDO PARAMO |
| Final | 8/11/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |