1020 1/2 E 83RD ST 90001

Certificate Information: 1020 1/2 E 83RD ST 90001

Application / Permit
21016-10000-19897
Plan Check / Job No.
B21LA14291
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED 3-CAR GARAGE AND WORK ROOM TO ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c)-(d) **SEE APPLICATION COMMENTS**
Permit Issued
Issued on 10/12/2022
Issuing Office
Metro
Current Status
Issued on 10/12/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/9/2021 APPLICANT
Assigned to Plan Check Engineer 8/10/2021 LUKE GONZALES
Corrections Issued 8/10/2021 LUKE GONZALES
Applicant returned to address corrections 12/29/2021 GEORGE ALVAREZ
Applicant returned to address corrections 2/20/2022 FARSHAD ALIMOHAMADI
Building Plans Picked Up 2/23/2022 APPLICANT
Plan Check Approved 3/8/2022 JOSEPH RAFOLS
Issued 10/12/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/1/2022 CELINA MORENO
Roof/Waste drainage to street Cleared 2/1/2022 CELINA MORENO
Sewer availability Cleared 2/1/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/2/2022 CELINA MORENO
Hydrant and Access approval Cleared 3/8/2022 MENOA AGHAJANI
Tenant Habitability Plan Cleared 3/8/2022 TERRI ALEXANDER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 2/21/2023 Corrections Issued DONALD CRICHLOW
Wood Frame 2/21/2023 Not Ready for Inspection ALAN MORELOS
Pre-Inspection 3/1/2023 Partial Inspection LILIANA PORTILLO
Pre-Inspection 3/13/2023 Partial Inspection LILIANA PORTILLO
Footing/Foundation/Slab 6/28/2023 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 10/13/2023 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 10/31/2023 Corrections Issued MICHAEL LEWIS
Wood Frame 1/14/2025 Not Ready for Inspection JOHN QUINTANILLA
Wood Frame 2/5/2025 Partial Inspection JOHN QUINTANILLA
Interior/Exterior Lathing 2/20/2025 Approved JOHN QUINTANILLA
Wood Frame 2/20/2025 Partial Inspection JOHN QUINTANILLA
Wood Frame 6/9/2025 Not Ready for Inspection JOHN QUINTANILLA
Insulation 8/19/2025 Partial Approval JOHN QUINTANILLA
Insulation 8/27/2025 No Access for Inspection ANTHONY RAMOS
Insulation 9/5/2025 Not Ready for Inspection RONNIE MEDINA
Insulation 12/9/2025 Approved ANTHONY RAMOS
Wood Frame 12/9/2025 Approved ANTHONY RAMOS
Drywall Nailing 12/19/2025 Approved ANTHONY RAMOS
Special/Order Compliance 12/19/2025 Approved ANTHONY RAMOS
Final 2/26/2026 Corrections Issued JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 2/26/2026 SGSOV Not Ready JOHN QUINTANILLA
Smoke Detectors 2/26/2026 Approved JOHN QUINTANILLA
Final 4/23/2026 Not Ready for Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 4/23/2026 SGSOV Approved JOHN QUINTANILLA
Final 5/22/2026 Corrections Issued RAUL BARAJAS