- **Eplan** ** PROPOSED ADDITION TO CONNECT TWO DETACHED EXISTING DETACHED GARAGES INTO ONE BUILDING, TO CREATE AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33, AND A RECREATION ROOM. **See comments for Change of Address**
- Permit Issued
- Issued on 2/23/2023
- Issuing Office
- Current Status
- CofO Issued on 8/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | JOHNNY WU |
| Corrections Issued | 8/26/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 8/31/2021 | WING SUEN |
| Applicant returned to address corrections | 12/17/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 2/25/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 9/8/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 11/9/2022 | JOHNNY WU |
| Applicant returned to address corrections | 12/5/2022 | JOHNNY WU |
| Applicant returned to address corrections | 1/20/2023 | JOHNNY WU |
| Applicant returned to address corrections | 2/22/2023 | JOHNNY WU |
| Plan Check Approved | 2/22/2023 | JOHNNY WU |
| Issued | 2/23/2023 | APPLICANT |
| CofO in Progress | 7/27/2024 | SCOTT FINNILA |
| CofO in Progress | 7/29/2024 | SCOTT FINNILA |
| Permit Finaled | 8/13/2024 | RONALD MYRICK |
| CofO Issued | 8/13/2024 | RONALD MYRICK |
| Permit Finaled | 8/13/2024 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 11/22/2021 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 11/22/2021 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 11/22/2021 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 11/22/2021 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 5/7/2022 | RUEL COLE |
| Address approval | Cleared | 8/20/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 9/7/2022 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 9/8/2022 | MARCO SANCHEZ |
| Grading Pre-Inspection | Cleared | 9/9/2022 | KIRK LINKLATER |
| Address approval | Cleared | 9/17/2022 | STEVE MELGAR |
| GPI Written Notices | Cleared | 11/9/2022 | MICHAEL LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Santos,, Michael; Lic. No.: C77657 | 16202 ORION AVE CHINO, CA 91708 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/11/2023 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 4/11/2023 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 6/27/2023 | Corrections Issued | SCOTT FINNILA |
| Underground Mechanical | 6/29/2023 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 7/10/2023 | Approved | SCOTT FINNILA |
| ELECTRICAL-Rough | 10/11/2023 | Not Ready for Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 10/16/2023 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2023 | Partial Approval | SCOTT FINNILA |
| Rough-Elec/Plmb/HVAC | 10/30/2023 | Partial Approval | SCOTT FINNILA |
| Rough-Elec/Plmb/HVAC | 11/3/2023 | Corrections Issued | SCOTT FINNILA |
| Rough-Elec/Plmb/HVAC | 11/9/2023 | Partial Approval | SCOTT FINNILA |
| HVAC-Rough | 1/11/2024 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 1/17/2024 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 1/18/2024 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 1/18/2024 | Approved | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 1/18/2024 | Approved | CRAIG VAUGHAN |
| Insulation | 1/23/2024 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 2/7/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 2/7/2024 | Approved | JOSH MEISTER |
| Shower Pan | 2/7/2024 | Not Ready for Inspection | JOSH MEISTER |
| ELECTRICAL-Final | 4/5/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Sewer | 4/11/2024 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 5/1/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 5/1/2024 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 5/1/2024 | Approved | CRAIG VAUGHAN |
| Green Building Final | 5/1/2024 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 5/1/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 5/1/2024 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/1/2024 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 5/1/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 5/1/2024 | Approved | CRAIG VAUGHAN |
| Final | 6/5/2024 | Corrections Issued | CRAIG VAUGHAN |
| Service/Power Release | 6/5/2024 | Approved | CRAIG VAUGHAN |
| Final | 6/11/2024 | Conditional Approval | CRAIG VAUGHAN |
| Service/Power Release | 6/11/2024 | Approved | CRAIG VAUGHAN |
| Final | 7/12/2024 | OK to Issue CofO | CRAIG VAUGHAN |