627 N STANLEY AVE 90036
Certificate Information: 627 N STANLEY AVE 90036
- Application / Permit
- 21016-10000-19425
- Plan Check / Job No.
- B21LA13980
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE INTO ADU.
- Permit Issued
- Issued on 5/24/2022
- Issuing Office
- Current Status
- CofO Issued on 3/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | JOE VO |
| Corrections Issued | 7/29/2021 | JOE VO |
| Plan Check Approved | 12/20/2021 | JOE VO |
| Issued | 5/24/2022 | APPLICANT |
| CofO in Progress | 3/4/2024 | AMIR NAZARIAN |
| Permit Finaled | 3/8/2024 | DEROLD HAUFF |
| CofO Issued | 3/8/2024 | DEROLD HAUFF |
| Permit Finaled | 3/8/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2021 | CECILIO NAVARRO |
| Address approval | Cleared | 11/4/2021 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 11/4/2021 | WALLIE JONG |
Contact Information
| Contractor | Pacific Coast Developers; Lic. No.: 888234-B | 5249 BECKFORD AVENUE TARZANA, CA 91356 |
| Engineer | Standley,, Craig Erick; Lic. No.: NA87675 | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 6/9/2022 | Conditional Approval | ADAM ESCOTO |
| METHANE-Barrier | 6/13/2022 | Approved | JOSEPH MCGARRY |
| METHANE-Rough | 6/13/2022 | Approved | JOSEPH MCGARRY |
| Pre-Inspection | 6/13/2022 | Partial Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/25/2022 | Corrections Issued | JOSEPH MCGARRY |
| Wood Frame | 2/14/2023 | Corrections Issued | RUBEN SALAS |
| Insulation | 2/17/2023 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 4/12/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 6/20/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 6/20/2023 | Corrections Issued | LILIANA PORTILLO |
| Rough-Elec/Plmb/HVAC | 6/20/2023 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 6/20/2023 | SGSOV Not Ready | LILIANA PORTILLO |
| ELECTRICAL-Rough | 7/3/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 7/3/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 7/3/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 7/3/2023 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 7/20/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 7/20/2023 | Conditional Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/28/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/28/2023 | Corrections Issued | LILIANA PORTILLO |
| Green Building Rough | 8/28/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 8/28/2023 | Approved | LILIANA PORTILLO |
| Insulation | 8/28/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 8/28/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 11/15/2023 | Approved | LILIANA PORTILLO |
| Insulation | 11/15/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 11/17/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 2/1/2024 | Approved | LILIANA PORTILLO |
| Final | 2/1/2024 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 2/1/2024 | Approved | LILIANA PORTILLO |
| Green Building Rough | 2/1/2024 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 2/1/2024 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 2/1/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 2/14/2024 | Approved | AMIR NAZARIAN |
| HVAC-Final | 2/14/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Final | 2/14/2024 | Approved | AMIR NAZARIAN |
| Final | 2/26/2024 | Corrections Issued | AMIR NAZARIAN |
| Special/Order Compliance | 2/26/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 3/1/2024 | OK to Issue CofO | AMIR NAZARIAN |