10143-10145 N PARR AVE 91040

Certificate Information: 10143-10145 N PARR AVE 91040

Application / Permit
21016-10000-19379
Plan Check / Job No.
B21LA13952
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert (E) attached garage into one story JADU per GC Sections 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 11/20/2021
Issuing Office
Current Status
CofO Issued on 11/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/2/2021 APPLICANT
Assigned to Plan Check Engineer 8/4/2021 RAMA DABADGE
Corrections Issued 8/4/2021 RAMA DABADGE
Applicant returned to address corrections 9/20/2021 RICARDO RAMIREZ
Plan Check Approved 11/3/2021 JESSE JIMENEZ
Issued 11/20/2021 APPLICANT
Building Plans Picked Up 11/24/2021 APPLICANT
CofO in Progress 9/29/2023 DAVID ANDERSON
Permit Finaled 11/17/2023 RUBEN SALAS
CofO Issued 11/17/2023 RUBEN SALAS
Permit Finaled 11/17/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/12/2021 GABRIEL ROBLES
Sewer availability Cleared 8/12/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/17/2021 GABRIEL ROBLES
Grading Pre-Inspection Cleared 10/26/2021 PATRICK MISCHLICH
Hold Cleared 4/13/2022 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/18/2022 Approved CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 4/20/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 10/28/2022 Not Ready for Inspection DAVID ANDERSON
Final 10/28/2022 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 10/28/2022 Approved DAVID ANDERSON
Green Building Rough 10/28/2022 Corrections Issued DAVID ANDERSON
HVAC-Rough 10/28/2022 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 10/28/2022 Not Ready for Inspection DAVID ANDERSON
Interior/Exterior Lathing 11/7/2022 Approved DAVID ANDERSON
BUILDING-Rough-Frame 5/12/2023 Approved DAVID ANDERSON
Green Building Rough 5/12/2023 Approved DAVID ANDERSON
Rough-Elec/Plmb/HVAC 5/12/2023 Approved DAVID ANDERSON
Insulation 5/22/2023 Approved DAVID ANDERSON
Drywall Nailing 6/16/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 7/10/2023 Approved DAVID ANDERSON
Shower Pan 7/10/2023 Approved DAVID ANDERSON
Final 9/20/2023 Corrections Issued DAVID ANDERSON
Green Building Final 9/20/2023 Approved DAVID ANDERSON
Final 9/29/2023 OK to Issue CofO DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 9/29/2023 SGSOV Approved DAVID ANDERSON
Service/Power Release 9/29/2023 Approved DAVID ANDERSON
Smoke Detectors 9/29/2023 Approved DAVID ANDERSON