401 E CARROLL CL 90291
Certificate Information: 401 E CARROLL CL 90291
- Application / Permit
- 21016-10000-19324
- Plan Check / Job No.
- B21LA13922
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan : INSTALL NEW( 5'-5" X 8'-0") PREFAB SPA & NEW WET BAR AT (E) ROOF OF (E) 2 STYORY SINGLE FAMILY DWELLING & REPLACE & REPAIR (E) ROOF TOP DECK RAILING. ( SPA UNDER PERMIT APPLICATION # 22047-10000-00133) COMPLY WITH DEPARTMENT ORDER effective date 06/09/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 1/28/2022
- Issuing Office
- Current Status
- Permit Finaled on 11/29/2023
Permit Application Status History
| Submitted | 8/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2021 | GARO TELMI |
| Corrections Issued | 8/24/2021 | GARO TELMI |
| Quality Review Completed | 9/2/2021 | MICHAEL PEREZ |
| Plan Check Approved | 1/24/2022 | GARO TELMI |
| No Progress | 1/24/2022 | GARO TELMI |
| Plan Check Approved | 1/24/2022 | GARO TELMI |
| Issued | 1/28/2022 | APPLICANT |
| Permit Finaled | 11/29/2023 | JOHN MATTILLO |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 11/12/2021 | BINDU KANNAN |
| Miscellaneous | Cleared | 11/12/2021 | BINDU KANNAN |
| Specific Plan | Cleared | 11/12/2021 | BINDU KANNAN |
| Coastal Zone | Cleared | 11/23/2021 | DANIEL CORONADO |
| Miscellaneous | Cleared | 11/23/2021 | DANIEL CORONADO |
| Miscellaneous | Cleared | 11/23/2021 | DANIEL CORONADO |
Contact Information
| Architect | , ; Lic. No.: C35166 | 16800 DEVONSHIRE ST 307 GRANADA HILLS, CA 91344 |
| Contractor | Lyons Development; Lic. No.: 969576-B | 8560 W SUNSET BLVD STE 424 WEST HOLLYWOOD, CA 90069 |
| Engineer | Padilla,, Joseph G; Lic. No.: C72117 | 1553 PICASSO LN OXNARD, CA 93033 |
| Engineer | Wong,, Joseph Lo; Lic. No.: C69576 | 1235 ENCINA DR MILLBRAE, CA 94030 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/22/2022 | Approved | MARIAN PODPORA |
| Footing/Foundation/Slab | 4/14/2022 | Partial Approval | JOHN MATTILLO |
| Deputy Drilled-In Anchors | 4/25/2022 | Conditional Approval | JOHN MATTILLO |
| Footing/Foundation/Slab | 4/26/2022 | Approved | MARIAN PODPORA |
| Deputy Reinf. Concrete | 5/2/2022 | Conditional Approval | MARIAN PODPORA |
| Deputy Wood Construction | 5/9/2022 | Conditional Approval | JOHN MATTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Partial Approval | MARIAN PODPORA |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2022 | Corrections Issued | MARIAN PODPORA |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2022 | Partial Approval | MARIAN PODPORA |
| Drywall Nailing | 6/16/2022 | Not Ready for Inspection | MARIAN PODPORA |
| Drywall Nailing | 6/17/2022 | Partial Approval | MARIAN PODPORA |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2022 | Not Ready for Inspection | RYAN BARNES |
| Interior/Exterior Lathing | 7/5/2022 | Approved | RYAN BARNES |
| Deputy Wood Construction | 7/18/2022 | Conditional Approval | JOHN MATTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2022 | Approved | JOHN MATTILLO |
| Final | 9/21/2022 | No Access for Inspection | MARIAN PODPORA |
| SGSOV-Seismic Gas S/O Valve | 9/21/2022 | SGSOV Not Ready | MARIAN PODPORA |
| Smoke Detectors | 9/21/2022 | No Access for Inspection | MARIAN PODPORA |
| Final | 9/23/2022 | Corrections Issued | MARIAN PODPORA |
| SGSOV-Seismic Gas S/O Valve | 9/23/2022 | SGSOV Approved | MARIAN PODPORA |
| Smoke Detectors | 9/23/2022 | Approved | MARIAN PODPORA |
| Final | 10/31/2022 | No Access for Inspection | RYAN BARNES |
| HVAC-Final | 10/31/2022 | No Access for Inspection | RYAN BARNES |
| HVAC-Rough | 10/31/2022 | No Access for Inspection | RYAN BARNES |
| ELECTRICAL-Final | 11/1/2022 | Approved | RYAN BARNES |
| HVAC-Final | 11/1/2022 | Not Ready for Inspection | RYAN BARNES |
| HVAC-Rough | 11/1/2022 | Corrections Issued | RYAN BARNES |
| PLUMBING-Final | 11/1/2022 | Approved | RYAN BARNES |
| Final | 11/3/2022 | Corrections Issued | MARIAN PODPORA |
| HVAC-Final | 11/3/2022 | Corrections Issued | MARIAN PODPORA |
| Deputy Wood Construction | 11/22/2022 | Approved | MARIAN PODPORA |
| Final | 11/22/2022 | Corrections Issued | MARIAN PODPORA |
| HVAC-Final | 11/22/2022 | Corrections Issued | MARIAN PODPORA |
| Final | 11/29/2023 | Permit Finaled | JOHN MATTILLO |