4005 W JEFFERSON BLVD 90016

Certificate Information: 4005 W JEFFERSON BLVD 90016

Application / Permit
21016-10000-18992
Plan Check / Job No.
B21LA13729
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
CHANGE OF USE FROM G-1 (12) MANUFACTURING USE TO OFFICE/B OCCUPANCY. ADD NEW ACCESSIBLE ENTRY AT ALLEY. ENLARGE AND ADD GLAZING TO W JEFFERSON BLVD.
Permit Issued
Issued on 4/4/2023
Issuing Office
Current Status
CofO Issued on 5/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 JOE VO
Corrections Issued 8/29/2021 JOE VO
Quality Review Completed 9/13/2021 MICHAEL PEREZ
Building Plans Picked Up 9/15/2021 APPLICANT
Disabled Access Plans Picked Up 9/15/2021 APPLICANT
Green Plans Picked Up 9/15/2021 APPLICANT
Applicant returned to address corrections 11/29/2021 JOE VO
Plan Check Approved 3/2/2023 JOE VO
Issued 4/4/2023 APPLICANT
CofO in Progress 4/29/2024 MARTIN TAVITIAN
CofO Issued 5/1/2024 ERNESTO CORRAL
Permit Finaled 5/1/2024 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/10/2021 THOMAS LANG
Sewer availability Cleared 9/10/2021 THOMAS LANG
Redevelopment Project Area Cleared 10/8/2021 DAVID URITA
Bicycle Parking Cleared 10/30/2021 JEREMY CHOK
Green Code Cleared 11/15/2021 AARON COSTA
Hydrant and Access approval Cleared 11/29/2021 KURT CORRAL
DAS Clearance Cleared 3/17/2022 JOE VO
Bicycle Parking Cleared 3/23/2022 PETE EYRE
Flood clearance Cleared 2/8/2023 SAMSON WONG
Community Plan Implem. Overlay Cleared 2/14/2023 KYLE WINSTON

Contact Information

Contractor City Constructors Inc; Lic. No.: 834591-B 450 S RAYMOND AVENUE      PASADENA, CA 91105
Engineer Alexander,, Andy; Lic. No.: C84086 1615 GRAMERCY AVE      TORRANCE, CA 90501

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/3/2023 Approved ALFREDO LOPEZ
Footing/Foundation/Slab 6/21/2023 Partial Approval MARTIN TAVITIAN
Excavation/Setback/Form/Re-Bar 6/27/2023 Not Ready for Inspection ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 6/28/2023 Partial Inspection ALFREDO LOPEZ
Reinforced Concrete Frame 6/28/2023 Partial Inspection ALFREDO LOPEZ
Wood Frame 7/11/2023 Partial Approval ALFREDO LOPEZ
Special/Order Compliance 8/24/2023 Approved ALFREDO LOPEZ
Deputy Reinf. Concrete 9/13/2023 Conditional Approval ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 9/13/2023 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 9/13/2023 Not Ready for Inspection DARRYL ARNOLD
Light Gage Steel Frame 10/11/2023 Partial Approval ALFREDO LOPEZ
Light Gage Steel Frame 10/25/2023 Partial Approval ALFREDO LOPEZ
Insulation 10/27/2023 Approved JACOB MYERS
Drywall Nailing 11/1/2023 Partial Approval ALFREDO LOPEZ
Drywall Nailing 11/2/2023 Approved JACOB MYERS
Final 4/11/2024 OK to Issue CofO MARTIN TAVITIAN
Green Building Final 4/11/2024 Approved MARTIN TAVITIAN
Green Building Rough 4/11/2024 Approved MARTIN TAVITIAN
METHANE-Final 4/11/2024 Approved MARTIN TAVITIAN
METHANE-Rough 4/11/2024 Approved MARTIN TAVITIAN
Reinforced Masonry Frame 4/11/2024 Approved MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 4/11/2024 SGSOV Not Required MARTIN TAVITIAN
Smoke Detectors 4/11/2024 Approved MARTIN TAVITIAN