1907 W 84TH ST 90047
Certificate Information: 1907 W 84TH ST 90047
- Application / Permit
- 21016-10000-18972
- Plan Check / Job No.
- B21LA13721
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Convertion of (E) Recreation room w/ addition to create ADU per GCS 65852.2 and 65852.22
- Permit Issued
- Issued on 11/18/2021
- Issuing Office
- Current Status
- CofO Issued on 11/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/27/2021 | HERNAN ARREOLA |
| Corrections Issued | 7/27/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/18/2021 | HERNAN ARREOLA |
| Plan Check Approved | 10/25/2021 | HERNAN ARREOLA |
| Issued | 11/18/2021 | APPLICANT |
| CofO in Progress | 11/26/2024 | AMIR NAZARIAN |
| Permit Finaled | 11/30/2024 | DEROLD HAUFF |
| CofO Issued | 11/30/2024 | DEROLD HAUFF |
| Permit Finaled | 11/30/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/16/2021 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 8/16/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 8/17/2021 | STEVE MELGAR |
| Construction near power lines | Cleared | 10/20/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/23/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 6/27/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Sewer | 6/30/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 6/30/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 10/1/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Final | 10/1/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Final | 10/1/2024 | Corrections Issued | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 11/5/2024 | Approved | AMIR NAZARIAN |
| Drywall Nailing | 11/5/2024 | Approved | AMIR NAZARIAN |
| ELECTRICAL-Final | 11/5/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 11/5/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 11/5/2024 | Approved | AMIR NAZARIAN |
| Gas Test | 11/5/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Green Building Final | 11/5/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 11/5/2024 | Approved | AMIR NAZARIAN |
| HVAC-Final | 11/5/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Final | 11/5/2024 | Approved | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 11/5/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| Service/Power Release | 11/5/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Smoke Detectors | 11/5/2024 | Approved | AMIR NAZARIAN |
| Final | 11/22/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Final | 11/22/2024 | Approved | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 11/22/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| ELECTRICAL-Final | 11/25/2024 | Approved | AMIR NAZARIAN |
| Final | 11/25/2024 | OK to Issue CofO | AMIR NAZARIAN |
| Pre-Inspection | 11/25/2024 | Approved | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 11/25/2024 | SGSOV Approved | AMIR NAZARIAN |