1907 W 84TH ST 90047

Certificate Information: 1907 W 84TH ST 90047

Application / Permit
21016-10000-18972
Plan Check / Job No.
B21LA13721
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Convertion of (E) Recreation room w/ addition to create ADU per GCS 65852.2 and 65852.22
Permit Issued
Issued on 11/18/2021
Issuing Office
Current Status
CofO Issued on 11/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/23/2021 APPLICANT
Assigned to Plan Check Engineer 7/27/2021 HERNAN ARREOLA
Corrections Issued 7/27/2021 HERNAN ARREOLA
Applicant returned to address corrections 8/18/2021 HERNAN ARREOLA
Plan Check Approved 10/25/2021 HERNAN ARREOLA
Issued 11/18/2021 APPLICANT
CofO in Progress 11/26/2024 AMIR NAZARIAN
Permit Finaled 11/30/2024 DEROLD HAUFF
CofO Issued 11/30/2024 DEROLD HAUFF
Permit Finaled 11/30/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/16/2021 STEVE MELGAR
Roof/Waste drainage to street Cleared 8/16/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/17/2021 STEVE MELGAR
Sewer availability Cleared 8/17/2021 STEVE MELGAR
Construction near power lines Cleared 10/20/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Truong,, Phong; Lic. No.: C70784 20439 E CRESTLINE DRIVE      WALNUT, CA 91789

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/23/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 6/27/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Sewer 6/30/2022 Approved ENRIQUE MIRELES
Underground Mechanical 6/30/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Final 10/1/2024 Corrections Issued AMIR NAZARIAN
HVAC-Final 10/1/2024 Corrections Issued AMIR NAZARIAN
PLUMBING-Final 10/1/2024 Corrections Issued AMIR NAZARIAN
BUILDING-Rough-Frame 11/5/2024 Approved AMIR NAZARIAN
Drywall Nailing 11/5/2024 Approved AMIR NAZARIAN
ELECTRICAL-Final 11/5/2024 Corrections Issued AMIR NAZARIAN
Final 11/5/2024 Corrections Issued AMIR NAZARIAN
Footing/Foundation/Slab 11/5/2024 Approved AMIR NAZARIAN
Gas Test 11/5/2024 Not Ready for Inspection AMIR NAZARIAN
Green Building Final 11/5/2024 Corrections Issued AMIR NAZARIAN
Green Building Rough 11/5/2024 Approved AMIR NAZARIAN
HVAC-Final 11/5/2024 Approved AMIR NAZARIAN
PLUMBING-Final 11/5/2024 Approved AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 11/5/2024 SGSOV Not Ready AMIR NAZARIAN
Service/Power Release 11/5/2024 Not Ready for Inspection AMIR NAZARIAN
Smoke Detectors 11/5/2024 Approved AMIR NAZARIAN
Final 11/22/2024 Corrections Issued AMIR NAZARIAN
Green Building Final 11/22/2024 Approved AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 11/22/2024 SGSOV Not Ready AMIR NAZARIAN
ELECTRICAL-Final 11/25/2024 Approved AMIR NAZARIAN
Final 11/25/2024 OK to Issue CofO AMIR NAZARIAN
Pre-Inspection 11/25/2024 Approved AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 11/25/2024 SGSOV Approved AMIR NAZARIAN