700 N ALAMEDA ST 90744
Certificate Information: 700 N ALAMEDA ST 90744
- Application / Permit
- 21016-10000-18957
- Plan Check / Job No.
- B21LA13706
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- ePlan 2hr Rated Closets for Fire Alarm Equipment at Levels 1-12 (High Rise) and Levels 1, 2 and 4 (Low Rise)
- Permit Issued
- Issued on 1/4/2022
- Issuing Office
- Current Status
- Issued on 1/4/2022
Permit Application Status History
| Submitted | 7/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | HERNAN ARREOLA |
| Corrections Issued | 8/19/2021 | HERNAN ARREOLA |
| Quality Review Completed | 8/23/2021 | JASON HEALEY |
| Plan Check Approved | 11/8/2021 | HERNAN ARREOLA |
| Issued | 1/4/2022 | APPLICANT |
Permit Application Clearance Information
| City owned building/parcel | Cleared | 10/1/2021 | HERNAN ARREOLA |
| Fire Marshal Fire Life Safety | Cleared | 11/17/2021 | ANDREW KO |
Contact Information
| Architect | Budetti,, Robert Peter; Lic. No.: C23757 | 601 N CEDROS AVE SOLANO BEACH, CA 92075 |
| Contractor | Bernards Bros Inc; Lic. No.: 302007-B | , |
| Engineer | Allen,, Thomas Christopher; Lic. No.: S5460 | 2 VENTURE, SUITE 200 IRVINE, CA 92618 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 1/12/2022 | Approved | JOEY BUCHANAN |
| Smoke Detectors | 4/6/2022 | Partial Approval | MARK FERRARI |
| Smoke Detectors | 5/12/2022 | Partial Approval | MARK FERRARI |
| Smoke Detectors | 5/17/2022 | Partial Approval | MARK FERRARI |
| Smoke Detectors | 6/7/2022 | Partial Approval | MARK FERRARI |
| Smoke Detectors | 6/16/2022 | Partial Approval | MARK FERRARI |
| Smoke Detectors | 7/11/2022 | Partial Approval | MARK FERRARI |
| Pre-Inspection | 7/14/2022 | Partial Approval | MARK FERRARI |
| Smoke Detectors | 7/22/2022 | Partial Approval | MARK FERRARI |
| Pre-Inspection | 7/26/2022 | Partial Approval | MARK FERRARI |
| Smoke Detectors | 8/2/2022 | Partial Approval | MARK FERRARI |
| Smoke Detectors | 8/18/2022 | Partial Approval | MARK FERRARI |
| Smoke Detectors | 9/12/2022 | Partial Approval | MARK FERRARI |
| Pre-Inspection | 9/15/2022 | Partial Approval | MARK FERRARI |
| Smoke Detectors | 10/19/2022 | Partial Approval | MARK FERRARI |
| Drywall Nailing | 11/1/2022 | Partial Approval | MARK FERRARI |
| Light Gage Steel Frame | 11/1/2022 | Approved | MARK FERRARI |
| Drywall Nailing | 11/10/2022 | Partial Approval | MARK FERRARI |
| Drywall Nailing | 11/15/2022 | Not Ready for Inspection | MARK FERRARI |
| Drywall Nailing | 11/28/2022 | Partial Approval | MARK FERRARI |
| Drywall Nailing | 12/1/2022 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 12/7/2022 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 12/15/2022 | Partial Approval | MARK FERRARI |
| Drywall Nailing | 12/22/2022 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 12/29/2022 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 1/6/2023 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 1/13/2023 | Approved | RAMAZANALI ALMASI |
| Drywall Nailing | 1/19/2023 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 1/25/2023 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 2/1/2023 | Partial Approval | JULIAN CAPUCETTI |
| Drywall Nailing | 2/8/2023 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 2/16/2023 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 2/17/2023 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 2/28/2023 | Approved | JULIAN CAPUCETTI |
| Special/Order Compliance | 4/6/2023 | Approved | JULIAN CAPUCETTI |
| Special/Order Compliance | 3/13/2024 | Partial Approval | RAMAZANALI ALMASI |