6505 W 87TH PL 90045

Certificate Information: 6505 W 87TH PL 90045

Application / Permit
21016-10000-18675
Plan Check / Job No.
B21LA13558
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODELING OF SFD. FULL KITCHEN AND TWO BATHROOMS. REMOVE PORTION OF BEARING WALL WITH POSTS AND BEAM.
Permit Issued
Issued on 9/15/2021
Issuing Office
Current Status
Permit Finaled on 1/12/2023

Permit Application Status History

Submitted 7/20/2021 APPLICANT
Assigned to Plan Check Engineer 7/26/2021 JESSE JIMENEZ
Corrections Issued 7/28/2021 JESSE JIMENEZ
Building Plans Picked Up 8/2/2021 APPLICANT
Applicant returned to address corrections 9/8/2021 RAHEL BEYENE
Plan Check Approved 9/10/2021 RAHEL BEYENE
Issued 9/15/2021 APPLICANT
Permit Finaled 1/12/2023 MARIAN PODPORA

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Samara,, Muzahim Ali; Lic. No.: C26015 9100 S SEPULVEDA BLVD SUITE 115      LOS ANGELES, CA 90045

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

HVAC-Rough 9/28/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 9/28/2021 Not Ready for Inspection BRENDAN LOONEY
Pre-Inspection 9/28/2021 Corrections Issued BRENDAN LOONEY
Rough-Elec/Plmb/HVAC 10/13/2021 Corrections Issued MARIAN PODPORA
Rough-Elec/Plmb/HVAC 10/26/2021 Partial Approval MARIAN PODPORA
Deputy Drilled-In Anchors 12/7/2021 Conditional Approval MARIAN PODPORA
Rough-Elec/Plmb/HVAC 12/8/2021 Corrections Issued MARIAN PODPORA
Insulation 12/10/2021 Not Ready for Inspection MARIAN PODPORA
PLUMBING-Rough 12/10/2021 Approved MARIAN PODPORA
Insulation 12/22/2021 Approved MARIAN PODPORA
Interior/Exterior Lathing 12/22/2021 Partial Approval MARIAN PODPORA
Shower Pan 12/22/2021 Approved MARIAN PODPORA
Drywall Nailing 12/28/2021 Approved MARIAN PODPORA
Interior/Exterior Lathing 12/28/2021 Approved MARIAN PODPORA
ELECTRICAL-Rough 1/14/2022 Partial Approval MARIAN PODPORA
ELECTRICAL-Final 3/4/2022 Corrections Issued MARIAN PODPORA
Final 3/4/2022 Corrections Issued MARIAN PODPORA
HVAC-Final 3/4/2022 Corrections Issued MARIAN PODPORA
PLUMBING-Final 3/4/2022 Approved MARIAN PODPORA
SGSOV-Seismic Gas S/O Valve 3/4/2022 SGSOV Approved MARIAN PODPORA
Smoke Detectors 3/4/2022 Approved MARIAN PODPORA
Final 3/16/2022 Corrections Issued MARIAN PODPORA
Final 3/18/2022 Corrections Issued MARIAN PODPORA
Final 1/12/2023 Permit Finaled MARIAN PODPORA