5131 S VICTORIA AVE 90043
Certificate Information: 5131 S VICTORIA AVE 90043
- Application / Permit
- 21016-10000-18576
- Plan Check / Job No.
- B21LA13468
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE IN TO (N) DETACHED ADU
- Permit Issued
- Issued on 9/27/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 7/28/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 4/22/2022 | RACHEL BEYENE |
| Building Plans Picked Up | 5/27/2022 | APPLICANT |
| Applicant returned to address corrections | 9/19/2022 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 9/27/2022 | FERNANDO FLORES |
| Issued | 9/27/2022 | APPLICANT |
| CofO in Progress | 10/5/2023 | ANTHONY EGSON |
| CofO Issued | 10/9/2023 | DEROLD HAUFF |
| Permit Finaled | 10/9/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/13/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2022 | CINDY QI |
| Hydrant and Access approval | Cleared | 6/13/2022 | LAVEON RIDER |
| Roof/Waste drainage to street | Cleared | 6/13/2022 | CINDY QI |
| Sewer availability | Cleared | 6/13/2022 | CINDY QI |
| Construction near power lines | Cleared | 8/25/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/14/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 12/14/2022 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 2/8/2023 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 2/8/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 2/8/2023 | Approved | STUART CHAPMAN |
| Wood Frame | 2/22/2023 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 3/1/2023 | Corrections Issued | ANTHONY EGSON |
| Insulation | 3/10/2023 | Approved | ANTHONY EGSON |
| Deputy Wood Construction | 3/13/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 3/15/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 3/15/2023 | Approved | ANTHONY EGSON |
| Insulation | 3/21/2023 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 3/21/2023 | Approved | ANTHONY EGSON |
| Drywall Nailing | 3/28/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/7/2023 | Approved | ANTHONY EGSON |
| Shower Pan | 4/7/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Gas Test | 4/13/2023 | Corrections Issued | ANTHONY EGSON |
| Sewer | 4/13/2023 | Corrections Issued | ANTHONY EGSON |
| Gas Test | 4/19/2023 | Partial Approval | ANTHONY EGSON |
| Sewer | 4/19/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/19/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 5/19/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 5/19/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 5/19/2023 | Approved | ANTHONY EGSON |
| HVAC-Final | 5/19/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 5/19/2023 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 5/19/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 5/19/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 5/31/2023 | Partial Approval | ANTHONY EGSON |
| Final | 5/31/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 5/31/2023 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 5/31/2023 | SGSOV Not Required | ANTHONY EGSON |
| Service/Power Release | 5/31/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Verify Rec and Parks Fee Memo | 5/31/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 6/5/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 6/5/2023 | Approved | ANTHONY EGSON |
| Service/Power Release | 6/5/2023 | Approved | ANTHONY EGSON |
| Final | 10/5/2023 | OK to Issue CofO | ANTHONY EGSON |