716 W 1ST ST 90012
Certificate Information: 716 W 1ST ST 90012
- Application / Permit
- 21016-10000-18354
- Plan Check / Job No.
- B21LA13321
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (10) Sanitarium
- Work Description
- TENANT IMPROVEMENT AND CHANGE OF USE FROM BANK INTO A (N) SANITARIUM.
- Permit Issued
- Issued on 11/1/2021
- Issuing Office
- Current Status
- CofO Issued on 3/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2021 | SINA KHOSRAVI |
| Corrections Issued | 7/24/2021 | SINA KHOSRAVI |
| Building Plans Picked Up | 7/30/2021 | APPLICANT |
| Applicant returned to address corrections | 9/8/2021 | SARKIS HARABEDIAN |
| Plan Check Approved | 10/26/2021 | PETER MOSESIAN |
| Issued | 11/1/2021 | APPLICANT |
| CofO in Progress | 3/10/2022 | TIMOTHY BUXTON |
| CofO Issued | 3/11/2022 | TED RIES |
| Permit Finaled | 3/11/2022 | TED RIES |
Permit Application Clearance Information
| ZA Case | Cleared | 8/9/2021 | PABLO ESTRADA |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2021 | THOMAS LANG |
| Sewer availability | Cleared | 8/16/2021 | THOMAS LANG |
| Specific Plan | Cleared | 9/27/2021 | YI LU |
| "D" conditions | Cleared | 9/28/2021 | MIGUEL GAMBOA |
Contact Information
| Architect | Mizuki,, Steve Massanori; Lic. No.: C22676 | 2155 VERDUGO BLVD # 330 MONTROSE, CA 91020 |
| Contractor | Archibuildz Llc; Lic. No.: 1052009-B | 2155 VERDUGO BLVD #330 MONTROSE, CA 91020 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 11/24/2021 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 11/30/2021 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 1/20/2022 | SGSOV Not Ready | TIMOTHY BUXTON |
| Final | 2/16/2022 | Not Ready for Inspection | TIMOTHY BUXTON |
| Light Gage Steel Frame | 2/16/2022 | Approved | TIMOTHY BUXTON |
| METHANE-Final | 2/16/2022 | Approved | TIMOTHY BUXTON |
| METHANE-Rough | 2/16/2022 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 2/16/2022 | SGSOV No Gas | TIMOTHY BUXTON |
| Smoke Detectors | 2/16/2022 | Approved | TIMOTHY BUXTON |
| Final | 2/28/2022 | Not Ready for Inspection | TIMOTHY BUXTON |
| Final | 3/1/2022 | Conditional Approval | TIMOTHY BUXTON |