3934 1/2 W BRUNSWICK AVE 90039
Certificate Information: 3934 1/2 W BRUNSWICK AVE 90039
- Application / Permit
- 21016-10000-18307
- Plan Check / Job No.
- B21LA13298
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of an (E) detached 2-car garage into an ADU per ordinance 186,481. Addition of covered patio to rear of new ADU.
- Permit Issued
- Issued on 12/7/2021
- Issuing Office
- Current Status
- CofO Issued on 3/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2021 | HELEN NGUYEN |
| Corrections Issued | 7/20/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/15/2021 | HELEN NGUYEN |
| Plan Check Approved | 11/16/2021 | HELEN NGUYEN |
| Issued | 12/7/2021 | APPLICANT |
| CofO in Progress | 3/1/2023 | HAMIK HARTOUNIAN |
| Permit Finaled | 3/11/2023 | DEROLD HAUFF |
| CofO Issued | 3/11/2023 | DEROLD HAUFF |
| Permit Finaled | 3/11/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/26/2021 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 7/26/2021 | CELINA MORENO |
| Sewer availability | Cleared | 7/26/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2021 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/22/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Pre-Inspection | 12/22/2021 | Partial Inspection | HAMIK HARTOUNIAN |
| Sewer | 12/22/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 1/14/2022 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 1/21/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/3/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 6/7/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 6/8/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2022 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/16/2022 | Approved | HAMIK HARTOUNIAN |
| Sewer | 6/16/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 6/29/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Rough-Elec/Plmb/HVAC | 6/29/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 6/29/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/1/2022 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 7/1/2022 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 7/1/2022 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/1/2022 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/10/2022 | Approved | HAMIK HARTOUNIAN |
| Insulation | 8/12/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Insulation | 8/25/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Wood Frame | 8/25/2022 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 9/1/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/6/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 12/8/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/8/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 12/8/2022 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 12/8/2022 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 12/8/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 12/27/2022 | Corrections Issued | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 12/27/2022 | SGSOV Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 12/30/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 12/30/2022 | Partial Inspection | HAMIK HARTOUNIAN |
| Final | 1/24/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 2/28/2023 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Service/Power Release | 2/28/2023 | Approved | HAMIK HARTOUNIAN |