3436 W HOLLYDALE DR 90039

Certificate Information: 3436 W HOLLYDALE DR 90039

Application / Permit
21016-10000-18141
Plan Check / Job No.
B21LA13190
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of (E) detached garage and storage into an ADU per state law GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 10/4/2021
Issuing Office
Current Status
CofO Issued on 4/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2021 APPLICANT
Assigned to Plan Check Engineer 7/16/2021 HELEN NGUYEN
Corrections Issued 7/20/2021 HELEN NGUYEN
Applicant returned to address corrections 8/9/2021 HELEN NGUYEN
Applicant returned to address corrections 8/23/2021 MONICA RAMIREZ
Applicant returned to address corrections 8/26/2021 HELEN NGUYEN
Applicant returned to address corrections 9/10/2021 HELEN NGUYEN
Plan Check Approved 9/14/2021 HELEN NGUYEN
Issued 10/4/2021 APPLICANT
CofO in Progress 3/22/2022 TIMOTHY MCCURDY
Permit Finaled 4/4/2022 DANIEL SANCHEZ
CofO Issued 4/4/2022 DANIEL SANCHEZ
Permit Finaled 4/4/2022 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 7/28/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/28/2021 WALLIE JONG
Sewer availability Cleared 7/28/2021 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

RUBEN PEREZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT NILES, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
MARK BEVELAQUA, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL SANCHEZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
COREY HUPP, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
EMIL OPFFER, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/1/2021 Partial Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/3/2021 Corrections Issued TIMOTHY MCCURDY
Special/Order Compliance 11/3/2021 Partial Inspection PIERRE VEGA
Excavation/Setback/Form/Re-Bar 11/24/2021 Approved TIMOTHY MCCURDY
ELECTRICAL-Rough 12/20/2021 Approved TIMOTHY MCCURDY
Footing/Foundation/Slab 12/20/2021 Approved TIMOTHY MCCURDY
HVAC-Rough 12/20/2021 Partial Approval TIMOTHY MCCURDY
PLUMBING-Rough 12/20/2021 Corrections Issued TIMOTHY MCCURDY
Special/Order Compliance 12/20/2021 Partial Inspection PIERRE VEGA
Wood Frame 12/20/2021 Corrections Issued TIMOTHY MCCURDY
PLUMBING-Rough 1/7/2022 Approved TIMOTHY MCCURDY
Wood Frame 1/7/2022 Approved TIMOTHY MCCURDY
Gas Test 1/11/2022 Approved TIMOTHY MCCURDY
Insulation 1/11/2022 Approved TIMOTHY MCCURDY
Drywall Nailing 1/18/2022 Approved TIMOTHY MCCURDY
BUILDING-Rough-Frame 2/8/2022 Approved TIMOTHY MCCURDY
ELECTRICAL-Rough 2/8/2022 Approved TIMOTHY MCCURDY
Final 2/8/2022 Corrections Issued TIMOTHY MCCURDY
Gas Test 2/8/2022 Approved TIMOTHY MCCURDY
HVAC-Final 2/8/2022 Approved TIMOTHY MCCURDY
PLUMBING-Rough 2/8/2022 Approved TIMOTHY MCCURDY
SGSOV-Seismic Gas S/O Valve 2/8/2022 SGSOV Not Ready TIMOTHY MCCURDY
Smoke Detectors 2/8/2022 Not Ready for Inspection TIMOTHY MCCURDY
SGSOV-Seismic Gas S/O Valve 2/25/2022 SGSOV Approved TIMOTHY MCCURDY
Service/Power Release 2/25/2022 Approved TIMOTHY MCCURDY
ELECTRICAL-Final 3/10/2022 Approved TIMOTHY MCCURDY
Final 3/10/2022 Partial Approval TIMOTHY MCCURDY
PLUMBING-Final 3/10/2022 Approved TIMOTHY MCCURDY
Smoke Detectors 3/10/2022 Approved TIMOTHY MCCURDY