5636 1/2 N SATSUMA AVE 91601

Certificate Information: 5636 1/2 N SATSUMA AVE 91601

Application / Permit
21016-10000-18079
Plan Check / Job No.
B21LA13156
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT AN EXISTING PERMITTED DETACHED GARAGE TO AN ADU. NO NEW FLOOR AREA.
Permit Issued
Issued on 11/7/2021
Issuing Office
Current Status
CofO Issued on 6/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/14/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 RACHEL BEYENE
Corrections Issued 7/15/2021 RACHEL BEYENE
Applicant returned to address corrections 8/27/2021 RACHEL BEYENE
Plan Check Approved 10/4/2021 TSE MING HUANG
Issued 11/7/2021 APPLICANT
Building Plans Picked Up 11/12/2021 APPLICANT
CofO in Progress 6/8/2023 JOHN HAYES
CofO Issued 6/9/2023 MICHAEL SMITH
Permit Finaled 6/9/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/14/2021 CECILIO NAVARRO
Sewer availability Cleared 8/14/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 8/17/2021 CECILIO NAVARRO

Contact Information

Architect Diradourian,, Richard C; Lic. No.: C10336 2618 HERMOSA AVENUE      MONTROSE, CA 91020
Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/22/2021 Approved JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 2/9/2022 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 4/8/2022 Partial Approval MATT KELLERMAN
Deputy Drilled-In Anchors 5/5/2022 Conditional Approval CALEB MEISTER
Green Building Rough 5/24/2022 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 5/24/2022 Partial Approval MISAEL ESPARZA
Green Building Rough 5/31/2022 Approved DAVID MATSON
Wood Frame 5/31/2022 Not Ready for Inspection DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 6/8/2022 Partial Approval ARAM AVEDISIAN
Insulation 6/8/2022 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 6/28/2022 Partial Approval CALEB MEISTER
Wood Frame 6/28/2022 Not Ready for Inspection CALEB MEISTER
Insulation 7/8/2022 Approved JOHN HAYES
Wood Frame 7/8/2022 Approved JOHN HAYES
Drywall Nailing 8/16/2022 Approved JOHN HAYES
Interior/Exterior Lathing 8/16/2022 Partial Approval JOHN HAYES
Final 4/7/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 4/7/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/7/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 4/7/2023 Approved JENNIFER RABUCHIN
Final 5/23/2023 Corrections Issued JOHN HAYES
Green Building Final 5/23/2023 Approved JOHN HAYES
Final 6/5/2023 No Access for Inspection JOHN HAYES
Final 6/7/2023 OK to Issue CofO JOHN HAYES