1885 W 96TH ST 90047
Certificate Information: 1885 W 96TH ST 90047
- Application / Permit
- 21016-10000-17951
- Plan Check / Job No.
- B21LA13035
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EXISTING GARAGE TO BE CONVERTED INTO AN ADU. 1 STORY PER STATE GCS 65852.2(e)(1)(A). ALL WORK PER WOOD FRAME PRESCRIPTIVE DESIGN.
- Permit Issued
- Issued on 5/20/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2021 | ZAW HAN |
| Corrections Issued | 8/30/2021 | ZAW HAN |
| Applicant returned to address corrections | 4/16/2022 | ZAW HAN |
| Plan Check Approved | 4/19/2022 | ZAW HAN |
| Building Plans Picked Up | 4/27/2022 | APPLICANT |
| Issued | 5/20/2022 | APPLICANT |
| CofO in Progress | 3/14/2024 | JOSE MACIAS |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
| CofO Issued | 3/29/2024 | DEROLD HAUFF |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/8/2021 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 9/8/2021 | THOMAS LANG |
| Sewer availability | Cleared | 9/8/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2021 | THOMAS LANG |
| Construction near power lines | Cleared | 11/19/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/13/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 10/26/2022 | Corrections Issued | RYAN SALAZAR |
| PLUMBING-Rough | 10/26/2022 | Partial Approval | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 12/15/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 1/3/2023 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 5/3/2023 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 5/3/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 6/14/2023 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 6/14/2023 | Approved | ENRIQUE MIRELES |
| Shower Pan | 6/14/2023 | Approved | ENRIQUE MIRELES |
| Wood Frame | 6/14/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 9/18/2023 | Approved | STUART CHAPMAN |
| Green Building Rough | 9/18/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 9/18/2023 | Approved | STUART CHAPMAN |
| Wood Frame | 9/18/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 12/29/2023 | Approved | ENRIQUE MIRELES |
| Final | 12/29/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 12/29/2023 | Approved | ENRIQUE MIRELES |
| METHANE-Final | 12/29/2023 | Approved | ENRIQUE MIRELES |
| METHANE-Rough | 12/29/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/29/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 12/29/2023 | Approved | ENRIQUE MIRELES |
| Final | 1/8/2024 | Corrections Issued | ENRIQUE MIRELES |
| Final | 3/13/2024 | OK to Issue CofO | JOSE MACIAS |