200 S GRAND AVE 90012

Certificate Information: 200 S GRAND AVE 90012

Application / Permit
21016-10000-17877
Plan Check / Job No.
B21LA12982
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(11) Dormitory
Work Description
ADDITION OF NEW NON LOAD BEARING PARTITIONS TO CREATE three NEW SLEEPING ROOMS WITHIN EXISTING SLEEPING SUITES OF DORMITORY. ADDITION OF NEW SINGLE USE RESTROOM WITH SHOWER IN EXISTING SLEEPING SUITE. RELOCATION OF EXISTING OUTLETS AND LIGHT FIXTURES TO COORDINATE WITH NEW PARTITION LOCATIONS. NEW PASSAGE SET DOORS TO SLEEPING ROOMS FOR PRIVACY. EXISTING PATH OF TRAVEL FROM STREET AND ACCESSIBLE PARKING TO REMAIN. EGRESS PATH TO REMAIN AS EXISTING.
Permit Issued
Issued on 10/26/2021
Issuing Office
Current Status
Issued on 10/26/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/12/2021 APPLICANT
Disabled Access Plans Picked Up 7/22/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 ARSALAN SHABESTARI
Corrections Issued 8/10/2021 ARSALAN SHABESTARI
Quality Review Completed 8/18/2021 MICHAEL PEREZ
Building Plans Picked Up 8/23/2021 APPLICANT
Applicant returned to address corrections 9/7/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 9/22/2021 ARSALAN SHABESTARI
Plan Check Approved 10/26/2021 PRANITA SHAH
Plan Check Approved 10/26/2021 ARSALAN SHABESTARI
Issued 10/26/2021 APPLICANT

Permit Application Clearance Information

DAS Clearance Cleared 8/5/2021 SHINE LIN
Specific Plan Cleared 9/13/2021 YI LU
Eng Process Fee Ord 176,300 Cleared 10/21/2021 JEANIE LAM
Sewer availability Cleared 10/21/2021 JEANIE LAM

Contact Information

Contractor Stanhope Robt W Co; Lic. No.: 127649-B 962 W TENTH STREET      AZUSA, CA 91702

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 11/4/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 11/5/2021 Approved TIMOTHY BUXTON
Light Gage Steel Frame 11/5/2021 Approved TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 11/17/2021 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 11/17/2021 Not Ready for Inspection KATY RAMIREZ
Final 11/23/2021 Conditional Approval TIMOTHY BUXTON
Smoke Detectors 11/23/2021 Approved TIMOTHY BUXTON
Final 12/2/2021 Conditional Approval TIMOTHY BUXTON