1401 W 8TH ST 90017

Certificate Information: 1401 W 8TH ST 90017

Application / Permit
21016-10000-17853
Plan Check / Job No.
B21LA12967
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
URM BLDG- NEW OPENING IN URM WALL. DEMOLITION OF INTERIOR TENANT FINISHES AND PARTITIONS FOR FUTURE TENANT SPACE. CHANGE OF USE FROM (E) RETAIL, MEDICAL OFFICE TO OFFICE AND PARKING GARAGE
Permit Issued
Issued on 12/23/2021
Issuing Office
Current Status
CofO Issued on 1/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 HERNAN ARREOLA
Corrections Issued 7/29/2021 HERNAN ARREOLA
Quality Review Completed 7/30/2021 JASON HEALEY
Building Plans Picked Up 8/2/2021 APPLICANT
Applicant returned to address corrections 8/11/2021 HERNAN ARREOLA
Disabled Access Plans Picked Up 8/13/2021 APPLICANT
Green Plans Picked Up 10/28/2021 APPLICANT
Applicant returned to address corrections 12/9/2021 HERNAN ARREOLA
Plan Check Approved 12/23/2021 HERNAN ARREOLA
Issued 12/23/2021 APPLICANT
CofO in Progress 1/4/2023 GREGORY POMISH
CofO Issued 1/4/2023 ERNESTO CORRAL
Permit Finaled 1/4/2023 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/3/2021 JEANIE LAM
Historic monument Cleared 8/3/2021 MELISSA JONES
Redevelopment Project Area Cleared 8/5/2021 DAVID URITA
"D" conditions Cleared 8/6/2021 DANIEL CORONADO
Green Code Cleared 10/21/2021 AARON COSTA
DAS Clearance Cleared 11/24/2021 EDDIE GARIN
Sewer availability Cleared 12/16/2021 AMAAN MALIK

Contact Information

Architect Miller,, Jeffrey A; Lic. No.: C37366 448B ROSECRANS AVENUE      MANHATTAN BEACH, CA 90266
Contractor Paracon Const Inc; Lic. No.: 963050-B 7319 SOMERSET BLVD      PARAMOUNT, CA 90723
Engineer Niaki,, Neman; Lic. No.: C46030 1107 CALIFORNIA AVE #2      SANTA MONICA, CA 90403

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/10/2022 Conditional Approval TIMOTHY BUXTON
Deputy Drilled-In Anchors 2/11/2022 Conditional Approval TIMOTHY BUXTON
Footing/Foundation/Slab 2/14/2022 Approved TIMOTHY BUXTON
Deputy Reinf. Concrete 2/15/2022 Conditional Approval TIMOTHY BUXTON
Deputy Reinf. Concrete 2/18/2022 Conditional Approval TIMOTHY BUXTON
Floor/Roof Diaphrgm/Shear Wall 3/14/2022 Approved TIMOTHY BUXTON
Footing/Foundation/Slab 4/19/2022 Corrections Issued TIMOTHY BUXTON
Light Gage Steel Frame 4/19/2022 Partial Approval TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 5/3/2022 Partial Approval TIMOTHY BUXTON
Deputy Reinf. Concrete 5/4/2022 Conditional Approval TIMOTHY BUXTON
Green Building Rough 5/13/2022 Approved TIMOTHY BUXTON
Wood Frame 5/13/2022 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 6/23/2022 Partial Inspection MARK FERRARI
Insulation 7/14/2022 Approved DARRYL ARNOLD
Drywall Nailing 7/15/2022 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 7/27/2022 Partial Approval KATY RAMIREZ
T-Bar Ceiling 8/31/2022 Partial Approval RUSSELL BONVOULOIR
T-Bar Ceiling 9/8/2022 Approved TIMOTHY BUXTON
Green Building Final 9/20/2022 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 9/20/2022 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 9/20/2022 Not Ready for Inspection KATY RAMIREZ
Special/Order Compliance 9/20/2022 Corrections Issued KATY RAMIREZ
Wood Frame 9/20/2022 Not Ready for Inspection KATY RAMIREZ
Special/Order Compliance 9/23/2022 Conditional Approval TIMOTHY BUXTON
Final 11/15/2022 Not Ready for Inspection KATY RAMIREZ
Green Building Final 11/15/2022 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 11/15/2022 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 11/15/2022 Not Ready for Inspection KATY RAMIREZ
Wood Frame 11/15/2022 Not Ready for Inspection KATY RAMIREZ
Final 11/17/2022 Not Ready for Inspection TIMOTHY BUXTON
Green Building Final 11/17/2022 Not Ready for Inspection TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 11/17/2022 SGSOV Not Ready TIMOTHY BUXTON
Smoke Detectors 11/17/2022 Approved TIMOTHY BUXTON
Pre-Inspection 11/22/2022 Approved GREGORY POMISH
Final 1/4/2023 OK to Issue CofO GREGORY POMISH
Green Building Final 1/4/2023 Approved GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 1/4/2023 SGSOV Approved GREGORY POMISH
Wood Frame 1/4/2023 Approved GREGORY POMISH