3641 1/2 E ROSEVIEW AVE 90065

Certificate Information: 3641 1/2 E ROSEVIEW AVE 90065

Application / Permit
21016-10000-17755
Plan Check / Job No.
B21LA12872
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing recreation room to a DETACHED accessory dwelling unit (439 SF). PER STATE LAW
Permit Issued
Issued on 11/10/2021
Issuing Office
Current Status
CofO Issued on 8/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 CARLOS MONTES
Corrections Issued 8/1/2021 CARLOS MONTES
Quality Review Completed 8/10/2021 PRANITA SHAH
Applicant returned to address corrections 9/21/2021 CARLOS MONTES
Applicant returned to address corrections 10/15/2021 CARLOS MONTES
Plan Check Approved 10/28/2021 CARLOS MONTES
Issued 11/10/2021 APPLICANT
CofO in Progress 6/27/2022 OSVALDO PARAMO
CofO in Progress 6/27/2022 OSVALDO PARAMO
Permit Finaled 8/23/2022 DEROLD HAUFF
CofO Issued 8/23/2022 DEROLD HAUFF
Permit Finaled 8/23/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/18/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/18/2021 JEANIE LAM
Sewer availability Cleared 8/18/2021 JEANIE LAM
Specific Plan Cleared 8/26/2021 DYLAN LAWRENCE
Miscellaneous Cleared 8/30/2021 RICHARD REASER
ZI Cleared 8/30/2021 RICHARD REASER
Grading Pre-Inspection Cleared 9/8/2021 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/4/2022 Approved OSVALDO PARAMO
Gas Test 2/14/2022 Not Ready for Inspection OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 2/14/2022 Corrections Issued OSVALDO PARAMO
Wood Frame 2/14/2022 Approved OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 3/4/2022 Approved OSVALDO PARAMO
Drywall Nailing 3/14/2022 Approved OSVALDO PARAMO
Shower Pan 3/14/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 5/23/2022 Approved OSVALDO PARAMO
Final 5/23/2022 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 5/23/2022 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 5/23/2022 Approved OSVALDO PARAMO
Final 6/1/2022 Not Ready for Inspection OSVALDO PARAMO
Final 6/8/2022 OK to Issue CofO OSVALDO PARAMO