3714 S MUIRFIELD ROAD 90016
Certificate Information: 3714 S MUIRFIELD ROAD 90016
- Application / Permit
- 21016-10000-17751
- Plan Check / Job No.
- B21LA12871
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN CONVERT (E) GARAGE TO ADU PER ORDINANCE 186481
- Permit Issued
- Issued on 11/4/2021
- Issuing Office
- Current Status
- CofO Issued on 3/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2021 | HERNAN ARREOLA |
| Corrections Issued | 7/12/2021 | HERNAN ARREOLA |
| Plan Check Approved | 10/17/2021 | HERNAN ARREOLA |
| Issued | 11/4/2021 | APPLICANT |
| CofO in Progress | 3/11/2026 | LUIS CASTRO |
| Permit Finaled | 3/12/2026 | DEROLD HAUFF |
| CofO Issued | 3/12/2026 | DEROLD HAUFF |
| Permit Finaled | 3/12/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/4/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2021 | JEANIE LAM |
| Sewer availability | Cleared | 8/4/2021 | JEANIE LAM |
| Construction near power lines | Cleared | 9/30/2021 | RIDWAN HARDY |
Contact Information
| Architect | Nichols,, Mark; Lic. No.: NA38099 | , |
| Contractor | N K Construction Inc; Lic. No.: 870801-B | 4470 W SUNSET BLVD #155 LOS ANGELES, CA 90027 |
| Engineer | Daoud,, Richard Antoine; Lic. No.: S6585 | 714 W OLYMPIC BLVD STE 617 LOS ANGELES, CA 90015 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/17/2021 | Conditional Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 11/19/2021 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Sewer | 11/19/2021 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 11/19/2021 | Approved | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 12/2/2021 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 12/10/2021 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 12/16/2021 | Approved | ADAM ESCOTO |
| BUILDING-Rough-Frame | 1/18/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 1/18/2022 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 1/27/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/27/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 1/27/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 1/27/2022 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/2/2022 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/2/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 2/2/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 2/2/2022 | Approved | FREDDIE RIVERA |
| Insulation | 2/3/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 2/8/2022 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 2/28/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 2/28/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 3/3/2022 | Approved | ANTHONY EGSON |
| Final | 10/26/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 10/26/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 10/26/2022 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 10/26/2022 | Approved | ANTHONY EGSON |
| Final | 11/2/2022 | Conditional Approval | ANTHONY EGSON |
| PLUMBING-Final | 11/2/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 11/2/2022 | SGSOV Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 3/10/2026 | Approved | LUIS CASTRO |
| Final | 3/10/2026 | OK to Issue CofO | LUIS CASTRO |
| HVAC-Final | 3/10/2026 | Approved | LUIS CASTRO |