254 S MANSFIELD AVE 90036
Certificate Information: 254 S MANSFIELD AVE 90036
- Application / Permit
- 21016-10000-17750
- Plan Check / Job No.
- B21LA12870
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE INTO ADU WITH ROOF DECK.
- Permit Issued
- Issued on 7/27/2022
- Issuing Office
- Current Status
- CofO Issued on 10/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | JOE VO |
| Corrections Issued | 7/31/2021 | JOE VO |
| Quality Review Completed | 8/10/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 5/12/2022 | JOE VO |
| Plan Check Approved | 6/21/2022 | JOE VO |
| Issued | 7/27/2022 | APPLICANT |
| CofO in Progress | 8/31/2023 | ROY SPAULDING |
| CofO Issued | 10/4/2023 | DEROLD HAUFF |
| Permit Finaled | 10/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/4/2021 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2021 | CINDY QI |
| Sewer availability | Cleared | 11/9/2021 | CINDY QI |
| Low Impact Development | Cleared | 11/10/2021 | JONATAN VELASQUEZ |
| Construction near power lines | Cleared | 2/17/2022 | RIDWAN HARDY |
| Construction near power lines | Cleared | 2/17/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/17/2022 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 6/8/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Ben Porat Moshe M; Lic. No.: 963181-B | , |
| Contractor | Moshe M Ben Porat; Lic. No.: 963181-B | , |
| Engineer | Lubberts,, Jeffrey Scott; Lic. No.: S6432 | 1548 KIRK AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/7/2022 | Partial Approval | JOSEPH MCGARRY |
| Underground Mechanical | 10/7/2022 | Partial Approval | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 10/11/2022 | Conditional Approval | MICHAEL LEWIS |
| Footing/Foundation/Slab | 10/14/2022 | Approved | JOSEPH MCGARRY |
| METHANE-Barrier | 10/14/2022 | Approved | JOSEPH MCGARRY |
| METHANE-Rough | 10/14/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| METHANE-Subgrade | 10/14/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 12/6/2022 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 12/6/2022 | Approved | STUART CHAPMAN |
| HVAC-Rough | 12/6/2022 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 12/6/2022 | Corrections Issued | STUART CHAPMAN |
| Sewer | 12/6/2022 | Approved | STUART CHAPMAN |
| Special/Order Compliance | 12/6/2022 | Approved | DONALD CRICHLOW |
| Underground Mechanical | 12/6/2022 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 12/12/2022 | Corrections Issued | RICHARD DOCKUS |
| Deputy Wood Construction | 12/12/2022 | Conditional Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 12/12/2022 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 12/12/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| METHANE-Rough | 12/12/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 12/12/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Wood Frame | 12/12/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 12/15/2022 | Partial Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 12/20/2022 | Corrections Issued | RICHARD DOCKUS |
| Gas Test | 12/20/2022 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 12/20/2022 | Approved | RICHARD DOCKUS |
| METHANE-Rough | 12/20/2022 | Approved | RICHARD DOCKUS |
| Shower Pan | 12/20/2022 | Approved | RICHARD DOCKUS |
| Wood Frame | 12/22/2022 | Partial Inspection | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 12/28/2022 | Corrections Issued | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2022 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 1/3/2023 | Corrections Issued | RICHARD DOCKUS |
| Interior/Exterior Lathing | 1/3/2023 | Partial Approval | RICHARD DOCKUS |
| Wood Frame | 1/3/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| Insulation | 1/11/2023 | Corrections Issued | RICHARD DOCKUS |
| Interior/Exterior Lathing | 1/12/2023 | Approved | RICHARD DOCKUS |
| Insulation | 1/17/2023 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 1/19/2023 | Corrections Issued | RICHARD DOCKUS |
| Insulation | 1/19/2023 | No Access for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 1/27/2023 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 1/27/2023 | Approved | RICHARD DOCKUS |
| Insulation | 1/27/2023 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 5/1/2023 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Final | 5/1/2023 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Final | 5/8/2023 | Approved | RICHARD DOCKUS |
| Final | 5/8/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Final | 5/8/2023 | Corrections Issued | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 5/8/2023 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 5/8/2023 | Approved | RICHARD DOCKUS |
| Final | 6/5/2023 | No Access for Inspection | RICHARD DOCKUS |
| Final | 6/14/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 6/29/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 7/31/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 7/31/2023 | Corrections Issued | LILIANA PORTILLO |
| Final | 8/4/2023 | Conditional Approval | LILIANA PORTILLO |
| HVAC-Final | 8/4/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 8/4/2023 | Approved | LILIANA PORTILLO |
| Final | 8/24/2023 | Not Ready for Inspection | ROY SPAULDING |
| Final | 8/30/2023 | OK to Issue CofO | ROY SPAULDING |