- ePLAN. CONVERT (E) ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) and 65852.22. NFPA 13D FIRE SPRINKLERS REQUIRED.
- Permit Issued
- Issued on 5/24/2022
- Issuing Office
- Current Status
- CofO Issued on 3/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2021 | KEVIN MORALES |
| Corrections Issued | 7/12/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 1/20/2022 | KEVIN MORALES |
| Plan Check Approved | 1/27/2022 | KEVIN MORALES |
| Issued | 5/24/2022 | APPLICANT |
| CofO in Progress | 3/1/2023 | VINCENT HANLEY |
| Permit Finaled | 3/3/2023 | JOHN JANSON |
| CofO Issued | 3/3/2023 | JOHN JANSON |
| Permit Finaled | 3/3/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/21/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/21/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Greeniron Constructs Inc; Lic. No.: 942902-B | 3200 AIRPORT AVENUE STE 20 SANTA MONICA, CA 90405 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/14/2022 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 9/1/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 9/1/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 9/1/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 9/1/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 9/1/2022 | Corrections Issued | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 9/13/2022 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 9/13/2022 | Corrections Issued | VINCENT HANLEY |
| Green Building Rough | 9/13/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 9/13/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 11/28/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 11/28/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 11/28/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 11/28/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 11/28/2022 | Partial Approval | VINCENT HANLEY |
| Insulation | 12/6/2022 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 12/6/2022 | Partial Approval | JESUS PINEDA |
| Drywall Nailing | 12/12/2022 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 12/12/2022 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 2/28/2023 | Approved | VINCENT HANLEY |
| Final | 2/28/2023 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 2/28/2023 | Approved | VINCENT HANLEY |
| HVAC-Final | 2/28/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 2/28/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/28/2023 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 2/28/2023 | Approved | VINCENT HANLEY |
| Special/Order Compliance | 2/28/2023 | Partial Inspection | JESUS PINEDA |