1425 S LIVONIA AVE 90035

Certificate Information: 1425 S LIVONIA AVE 90035

Application / Permit
21016-10000-17742
Plan Check / Job No.
B21LA12861
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Ground floor addition to an (E) detached garage and conversion of entire building into an ADU per ordinance 186,481. New attached trellis to the (N) ADU.
Permit Issued
Issued on 1/4/2022
Issuing Office
Current Status
CofO Issued on 11/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2021 APPLICANT
Assigned to Plan Check Engineer 7/14/2021 HELEN NGUYEN
Corrections Issued 7/15/2021 HELEN NGUYEN
Applicant returned to address corrections 9/8/2021 HELEN NGUYEN
Applicant returned to address corrections 10/9/2021 LAMAR DAVIS
Applicant returned to address corrections 10/26/2021 HELEN NGUYEN
Applicant returned to address corrections 11/22/2021 HELEN NGUYEN
Applicant returned to address corrections 12/8/2021 HELEN NGUYEN
Plan Check Approved 12/21/2021 HELEN NGUYEN
Issued 1/4/2022 APPLICANT
CofO in Progress 11/20/2023 MEL KHACHATOURIAN
Permit Finaled 11/20/2023 DANIEL ORRANTE
Permit Finaled 11/20/2023 DANIEL ORRANTE
CofO Issued 11/20/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/23/2021 BRIAN MILLER
GPI Written Notices Cleared 10/26/2021 HELEN NGUYEN
Sewer availability Cleared 11/5/2021 PAMELA TENEZA
Eng Process Fee Ord 176,300 Cleared 11/16/2021 PAMELA TENEZA
Low Impact Development Cleared 11/16/2021 LONDY ALVARADO
Address approval Cleared 11/20/2021 THOMAS LANG
Roof/Waste drainage to street Cleared 11/24/2021 THAN WIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/22/2023 Approved JEREMY TODD
Deputy Drilled-In Anchors 6/7/2023 Approved JEREMY TODD
METHANE-Subgrade 6/7/2023 Approved JEREMY TODD
Excavation/Setback/Form/Re-Bar 6/16/2023 Approved JEREMY TODD
Footing/Foundation/Slab 6/16/2023 Approved JEREMY TODD
METHANE-Barrier 6/16/2023 Approved JEREMY TODD
BUILDING-Rough-Frame 7/20/2023 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 7/20/2023 Approved ARAM AVEDISIAN
HVAC-Rough 7/20/2023 Approved ARAM AVEDISIAN
METHANE-Rough 7/20/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 7/20/2023 Approved ARAM AVEDISIAN
Insulation 7/25/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 7/25/2023 Partial Approval ARAM AVEDISIAN
Shower Pan 7/25/2023 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/27/2023 Approved ARAM AVEDISIAN
Drywall Nailing 8/1/2023 Approved ARAM AVEDISIAN
Green Building Rough 8/1/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 8/1/2023 Partial Approval ARAM AVEDISIAN
Underground Mechanical 9/8/2023 Approved BEN MOLSTAD
BUILDING-Rough-Frame 9/21/2023 Approved MEL KHACHATOURIAN
Final 9/21/2023 Corrections Issued MEL KHACHATOURIAN
Green Building Final 9/21/2023 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 9/21/2023 SGSOV Not Ready MEL KHACHATOURIAN
Smoke Detectors 9/21/2023 Approved MEL KHACHATOURIAN
Final 9/29/2023 Not Ready for Inspection MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 9/29/2023 SGSOV Approved MEL KHACHATOURIAN
Final 10/17/2023 Corrections Issued MICHAEL PELHAM
Final 11/21/2023 OK to Issue CofO MEL KHACHATOURIAN