1425 S LIVONIA AVE 90035
Certificate Information: 1425 S LIVONIA AVE 90035
- Application / Permit
- 21016-10000-17742
- Plan Check / Job No.
- B21LA12861
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Ground floor addition to an (E) detached garage and conversion of entire building into an ADU per ordinance 186,481. New attached trellis to the (N) ADU.
- Permit Issued
- Issued on 1/4/2022
- Issuing Office
- Current Status
- CofO Issued on 11/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2021 | HELEN NGUYEN |
| Corrections Issued | 7/15/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/8/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 10/9/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 10/26/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 11/22/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 12/8/2021 | HELEN NGUYEN |
| Plan Check Approved | 12/21/2021 | HELEN NGUYEN |
| Issued | 1/4/2022 | APPLICANT |
| CofO in Progress | 11/20/2023 | MEL KHACHATOURIAN |
| Permit Finaled | 11/20/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/20/2023 | DANIEL ORRANTE |
| CofO Issued | 11/20/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/23/2021 | BRIAN MILLER |
| GPI Written Notices | Cleared | 10/26/2021 | HELEN NGUYEN |
| Sewer availability | Cleared | 11/5/2021 | PAMELA TENEZA |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2021 | PAMELA TENEZA |
| Low Impact Development | Cleared | 11/16/2021 | LONDY ALVARADO |
| Address approval | Cleared | 11/20/2021 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 11/24/2021 | THAN WIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/22/2023 | Approved | JEREMY TODD |
| Deputy Drilled-In Anchors | 6/7/2023 | Approved | JEREMY TODD |
| METHANE-Subgrade | 6/7/2023 | Approved | JEREMY TODD |
| Excavation/Setback/Form/Re-Bar | 6/16/2023 | Approved | JEREMY TODD |
| Footing/Foundation/Slab | 6/16/2023 | Approved | JEREMY TODD |
| METHANE-Barrier | 6/16/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 7/20/2023 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 7/20/2023 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 7/20/2023 | Approved | ARAM AVEDISIAN |
| METHANE-Rough | 7/20/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/20/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 7/25/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/25/2023 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 7/25/2023 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2023 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 8/1/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 8/1/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 8/1/2023 | Partial Approval | ARAM AVEDISIAN |
| Underground Mechanical | 9/8/2023 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 9/21/2023 | Approved | MEL KHACHATOURIAN |
| Final | 9/21/2023 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Final | 9/21/2023 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 9/21/2023 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 9/21/2023 | Approved | MEL KHACHATOURIAN |
| Final | 9/29/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 9/29/2023 | SGSOV Approved | MEL KHACHATOURIAN |
| Final | 10/17/2023 | Corrections Issued | MICHAEL PELHAM |
| Final | 11/21/2023 | OK to Issue CofO | MEL KHACHATOURIAN |