950 E 3RD ST Bldg 3-unit 5 90013
Certificate Information: 950 E 3RD ST Bldg 3-unit 5 90013
- Application / Permit
- 21016-10000-17681
- Plan Check / Job No.
- B21LA12824
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- PROPOSING CHANGE OF USE FROM COMMERCIAL RETAIL TO RESTAURANT. TENANT IMPROVEMENT INCLUDING INTERIOR BUILD OUT OF THE RESTAURANT THAT INCLUDES NEW PARTITIONS, CEILING POWER & FINISHES, SUSHI PREP AREA, SUSHI BAR AND BACK OF HOUSE KITCHEN.
- Permit Issued
- Issued on 5/5/2022
- Issuing Office
- Current Status
- CofO Issued on 1/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | SERGIO GUTIERREZ |
| Corrections Issued | 8/18/2021 | SERGIO GUTIERREZ |
| Quality Review Completed | 8/20/2021 | FARUK SEZER |
| Disabled Access Plans Picked Up | 11/19/2021 | APPLICANT |
| Applicant returned to address corrections | 1/5/2022 | SERGIO GUTIERREZ |
| Plan Check Approved | 2/24/2022 | SERGIO GUTIERREZ |
| Issued | 5/5/2022 | APPLICANT |
| Building Plans Picked Up | 5/9/2022 | APPLICANT |
| CofO in Progress | 1/7/2025 | RONALD JIMENEZ |
| Permit Finaled | 1/7/2025 | ERNESTO CORRAL |
| CofO Issued | 1/7/2025 | ERNESTO CORRAL |
| Permit Finaled | 1/7/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Miscellaneous | Cleared | 8/31/2021 | RICHARD REASER |
| Miscellaneous | Cleared | 8/31/2021 | RICHARD REASER |
| Miscellaneous | Cleared | 8/31/2021 | RICHARD REASER |
| Miscellaneous | Cleared | 8/31/2021 | RICHARD REASER |
| Miscellaneous | Cleared | 8/31/2021 | RICHARD REASER |
| Miscellaneous | Cleared | 8/31/2021 | RICHARD REASER |
| Miscellaneous | Cleared | 8/31/2021 | RICHARD REASER |
| ZI | Cleared | 8/31/2021 | RICHARD REASER |
| Food Service Establishment | Cleared | 11/3/2021 | JASH PATEL |
| DAS Clearance | Cleared | 11/18/2021 | SERGIO GUTIERREZ |
| Food establishment approval | Cleared | 1/5/2022 | LACDHS APPROVED |
| ZA Case | Cleared | 2/15/2022 | OMAR GALACIA |
Contact Information
| Architect | Kamus,, John Howard; Lic. No.: C20397 | 5364 EVENING SKY DRIVE SIMI VALLEY, CA 93063 |
| Contractor | Bomar Russell Construction Services; Lic. No.: 751768-B | P O BOX 8314 LA VERNE, CA 91750 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/22/2022 | Corrections Issued | MARK FERRARI |
| Deputy Drilled-In Anchors | 11/30/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Wood Frame | 3/17/2023 | Approved | JULIAN CAPUCETTI |
| Drywall Nailing | 6/27/2023 | Approved | JULIAN CAPUCETTI |
| METHANE-Final | 3/18/2024 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 3/18/2024 | SGSOV Not Ready | RONALD JIMENEZ |
| Smoke Detectors | 3/18/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| T-Bar Ceiling | 3/18/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Final | 12/23/2024 | Conditional Approval | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 12/23/2024 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 12/23/2024 | Approved | RONALD JIMENEZ |
| Final | 1/7/2025 | OK to Issue CofO | RONALD JIMENEZ |