903 S CRENSHAW BLVD 90019
Certificate Information: 903 S CRENSHAW BLVD 90019
- Application / Permit
- 21016-10000-17670
- Plan Check / Job No.
- B21LA12813
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (15) Telecommunication Transmitter - wireless
- Work Description
- MODIFICATION TO AN (E) WIRELESS FACILITY PER ZA-98-0435 (CUZ) -REMOVE/REPLACE (E) SCREEN WALL WITH (N) SCREEN WALL -REMOVE/REPLACE 9 (E) RRUS WITH 6 (N) RRUS -INSTALL (N) ANGULAR FRAME AT EXTERIOR WALL OF BUILDING
- Permit Issued
- Issued on 11/1/2021
- Issuing Office
- Current Status
- Permit Finaled on 9/16/2022
Permit Application Status History
| Submitted | 7/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2021 | RICARDO RAMIREZ |
| Corrections Issued | 7/14/2021 | RICARDO RAMIREZ |
| Plan Check Approved | 8/31/2021 | RICARDO RAMIREZ |
| Issued | 11/1/2021 | APPLICANT |
| Building Plans Picked Up | 11/3/2021 | APPLICANT |
| Permit Finaled | 9/14/2022 | KATY RAMIREZ |
Permit Application Clearance Information
| "Q" conditions | Cleared | 8/17/2021 | DAVID URITA |
| "T" removal | Cleared | 8/17/2021 | DAVID URITA |
| Miscellaneous | Cleared | 8/17/2021 | DAVID URITA |
| Miscellaneous | Cleared | 8/17/2021 | DAVID URITA |
| Miscellaneous | Cleared | 8/17/2021 | DAVID URITA |
| Miscellaneous | Cleared | 8/17/2021 | DAVID URITA |
| Miscellaneous | Cleared | 8/17/2021 | DAVID URITA |
| Plan Approval | Cleared | 8/17/2021 | DAVID URITA |
| ZA Case | Cleared | 8/17/2021 | DAVID URITA |
Contact Information
| Contractor | Qualtek Wireless Llc; Lic. No.: 1042849-B | 475 SENTRY PKWAY E #200 BLUE BELL, PA 194222320 |
| Engineer | Lee,, Chris S; Lic. No.: C76549 | 400 S NORTON AVE A LOS ANGELES, CA 90020 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/13/2022 | Approved | KATY RAMIREZ |
| Wood Frame | 5/13/2022 | Partial Inspection | KATY RAMIREZ |
| Wood Frame | 5/18/2022 | Approved | KATY RAMIREZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Approved | KATY RAMIREZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2022 | Approved | SORIN CIRSTOIU |
| Wood Frame | 5/26/2022 | Approved | SORIN CIRSTOIU |
| Wood Frame | 6/1/2022 | Partial Approval | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 6/8/2022 | SGSOV Not Ready | KATY RAMIREZ |
| Final | 8/22/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/22/2022 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 8/22/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 9/14/2022 | Permit Finaled | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 9/14/2022 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 9/14/2022 | Approved | KATY RAMIREZ |