3956 S DUBLIN AVE 90008

Certificate Information: 3956 S DUBLIN AVE 90008

Application / Permit
21016-10000-17399
Plan Check / Job No.
B21LA12610
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
GARAGE CONVERSION TO ADU (18 X 18, 324 SQ FT, KITCHEN, BATHROOM, LAUNDRY ROOM).
Permit Issued
Issued on 5/12/2022
Issuing Office
Metro
Current Status
CofO Issued on 6/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2021 APPLICANT
Assigned to Plan Check Engineer 7/16/2021 TSE MING HUANG
Corrections Issued 7/17/2021 TSE MING HUANG
Applicant returned to address corrections 4/6/2022 TSE MING HUANG
Plan Check Approved 4/11/2022 TSE MING HUANG
Building Plans Picked Up 4/12/2022 APPLICANT
Issued 5/12/2022 APPLICANT
CofO in Progress 6/4/2024 ANTHONY EGSON
CofO Issued 6/10/2024 DEROLD HAUFF
Permit Finaled 6/10/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/22/2021 STEVE MELGAR
Sewer availability Cleared 11/22/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 12/27/2021 TREVOR QUAN
Construction near power lines Cleared 3/18/2022 TINA MIRANDA
Construction within easement Cleared 3/18/2022 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/19/2022 Approved ANTHONY EGSON
Footing/Foundation/Slab 7/21/2022 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 8/4/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 9/26/2022 No Access for Inspection ANTHONY EGSON
ELECTRICAL-Rough 9/26/2022 Corrections Issued ANTHONY EGSON
Green Building Rough 9/26/2022 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 9/26/2022 Approved ANTHONY EGSON
ELECTRICAL-Rough 10/20/2022 Approved ANTHONY EGSON
Gas Test 10/26/2022 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/3/2022 Corrections Issued ANTHONY EGSON
Green Building Rough 11/3/2022 Partial Approval ANTHONY EGSON
PLUMBING-Rough 11/3/2022 Approved ANTHONY EGSON
Deputy Wood Construction 11/7/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Approved ANTHONY EGSON
Green Building Rough 11/15/2022 Approved ANTHONY EGSON
Insulation 11/30/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 11/30/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/15/2022 Approved ANTHONY EGSON
Drywall Nailing 1/3/2023 Approved ANTHONY EGSON
Interior/Exterior Lathing 1/3/2023 Approved ANTHONY EGSON
Gas Test 7/20/2023 Not Ready for Inspection ANTHONY EGSON
Gas Test 7/31/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 8/4/2023 Corrections Issued ANTHONY EGSON
Green Building Final 8/4/2023 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 10/27/2023 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 2/2/2024 Approved ANTHONY EGSON
HVAC-Final 2/2/2024 Approved ANTHONY EGSON
PLUMBING-Final 2/2/2024 Approved ANTHONY EGSON
Green Building Final 2/29/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 3/4/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 3/15/2024 Approved BRENDAN MORELLI
Final 3/15/2024 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Final 4/1/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 4/16/2024 Approved ANTHONY EGSON
Green Building Final 4/16/2024 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 4/16/2024 SGSOV Approved ANTHONY EGSON
Smoke Detectors 4/16/2024 Approved ANTHONY EGSON
Final 6/3/2024 OK to Issue CofO ANTHONY EGSON