1510 W FLORENCE AVE 90047
Certificate Information: 1510 W FLORENCE AVE 90047
- Application / Permit
- 21016-10000-17347
- Plan Check / Job No.
- B21LA12579
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- INTERIOR ALTERATION TO REVISE THE FLOOR PLAN AND REMODELING OF THE EXISTING OFFICE.
- Permit Issued
- Issued on 11/18/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 5/3/2024
Permit Application Status History
| Submitted | 7/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 7/12/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 1/2/2022 | ZAW HAN |
| Plan Check Approved | 1/4/2022 | ZAW HAN |
| Building Plans Picked Up | 1/5/2022 | APPLICANT |
| Issued | 11/18/2022 | APPLICANT |
| Permit Finaled | 5/1/2024 | ALFREDO LOPEZ |
Permit Application Clearance Information
| Redevelopment Project Area | Cleared | 9/24/2021 | GRACIELA ACOSTA |
| Address approval | Cleared | 9/27/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 9/30/2021 | RENZ SORIANO |
| Community Plan Implem. Overlay | Cleared | 12/13/2021 | RAFAEL FONTES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Xia,, Ji; Lic. No.: C89014 | 420 S MADISON AVE APT 301 PASADENA, CA 91101 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 6/21/2023 | Partial Inspection | MICHAEL LEWIS |
| Pre-Inspection | 6/22/2023 | Partial Inspection | MARTIN TAVITIAN |
| Final | 1/11/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 1/11/2024 | SGSOV Not Ready | LUIS CCAMACHO |
| Smoke Detectors | 1/11/2024 | Approved | LUIS CCAMACHO |
| Final | 3/28/2024 | Partial Approval | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/28/2024 | SGSOV Approved | ALFREDO LOPEZ |
| Final | 5/1/2024 | Permit Finaled | ALFREDO LOPEZ |