213 1/2 N RENO ST 90026

Certificate Information: 213 1/2 N RENO ST 90026

Application / Permit
21016-10000-17335
Plan Check / Job No.
B21LA12555
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan -Soft-Story seismic retrofit per LABC Chapter 93: Install Three Hardy Frame Shear Walls
Permit Issued
Issued on 10/20/2021
Issuing Office
Current Status
CofC Issued on 12/28/2021

Permit Application Status History

Submitted 7/6/2021 APPLICANT
Assigned to Plan Check Engineer 7/21/2021 VARAND SARKISIAN
Corrections Issued 7/26/2021 VARAND SARKISIAN
Quality Review Completed 7/27/2021 HANS SANTIAGO
Plan Check Approved 8/13/2021 VARAND SARKISIAN
Issued 10/20/2021 APPLICANT
OK for CofC 12/23/2021 DARRYL ARNOLD
CofC Issued 12/28/2021 WINSTON DUNNING

Permit Application Clearance Information

Tenant Habitability Plan Cleared 9/17/2021 PHILLIP MUNGUIA

Contact Information

Contractor Xebec Construction; Lic. No.: 638225-B       ,
Engineer Namdar,, Mansour Tom; Lic. No.: NA2976       ,

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 11/9/2021 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 11/12/2021 Approved MARK FERRARI
Pre-Inspection 11/12/2021 Approved MARK FERRARI
Deputy Drilled-In Anchors 11/16/2021 Conditional Approval MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 11/18/2021 Approved MARK FERRARI
Wood Frame 11/18/2021 Approved MARK FERRARI
Interior/Exterior Lathing 11/29/2021 Corrections Issued BRUCE CAMPBELL
Final 12/23/2021 OK for CofC DARRYL ARNOLD
METHANE-Final 12/23/2021 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 12/23/2021 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 12/23/2021 Approved DARRYL ARNOLD