215 S BENTON WAY 90057
Certificate Information: 215 S BENTON WAY 90057
- Application / Permit
- 21016-10000-17096
- Plan Check / Job No.
- B21LA12411
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- E-PLAN: (N) 136 SF HOUSE ADDITION AND REMODEL TO AN (E) 1,484 SF SINGLE FAMILY RESIDENCE CONSTRUCTION TYPE V-B :
- Permit Issued
- Issued on 4/29/2022
- Issuing Office
- Current Status
- CofO Issued on 10/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 8/14/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 8/27/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 10/20/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 11/17/2021 | ARSALAN SHABESTARI |
| Issued | 4/29/2022 | APPLICANT |
| CofO in Progress | 10/9/2024 | FREDDIE RIVERA |
| Permit Finaled | 10/28/2024 | RUBEN SALAS |
| CofO Issued | 10/28/2024 | RUBEN SALAS |
| Permit Finaled | 10/28/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/2/2021 | WALLIE JONG |
| Sewer availability | Cleared | 9/2/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2021 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 10/8/2021 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: NA4978 | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/7/2022 | Corrections Issued | FREDDIE RIVERA |
| METHANE-Barrier | 9/7/2022 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Subgrade | 9/7/2022 | Partial Inspection | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 9/30/2022 | Conditional Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/6/2022 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 10/6/2022 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 10/6/2022 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/21/2022 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2022 | Partial Inspection | FREDDIE RIVERA |
| Insulation | 10/21/2022 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Corrections Issued | FREDDIE RIVERA |
| Insulation | 10/24/2022 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2022 | Partial Inspection | FREDDIE RIVERA |
| Insulation | 10/25/2022 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 12/8/2022 | Partial Inspection | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Partial Inspection | BRENDAN MORELLI |
| Green Building Rough | 12/8/2022 | Partial Inspection | BRENDAN MORELLI |
| METHANE-Rough | 12/8/2022 | Partial Inspection | BRENDAN MORELLI |
| Deputy Wood Construction | 12/30/2022 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2023 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/20/2023 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 3/20/2023 | Corrections Issued | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2023 | Corrections Issued | JEFFREY MEAD |
| Gas Test | 3/20/2023 | Partial Approval | JEFFREY MEAD |
| Green Building Rough | 3/20/2023 | Approved | JEFFREY MEAD |
| HVAC-Rough | 3/20/2023 | Corrections Issued | JEFFREY MEAD |
| Interior/Exterior Lathing | 3/20/2023 | Partial Approval | JEFFREY MEAD |
| METHANE-Rough | 3/20/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 3/20/2023 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 3/31/2023 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 3/31/2023 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 3/31/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 3/31/2023 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 4/7/2023 | Corrections Issued | FREDDIE RIVERA |
| Shower Pan | 4/7/2023 | Approved | FREDDIE RIVERA |
| Insulation | 5/2/2023 | Partial Inspection | FREDDIE RIVERA |
| Insulation | 6/2/2023 | Partial Inspection | FREDDIE RIVERA |
| Shower Pan | 6/2/2023 | No Access for Inspection | FREDDIE RIVERA |
| Drywall Nailing | 8/1/2023 | Partial Inspection | FREDDIE RIVERA |
| Drywall Nailing | 8/30/2023 | Approved | FREDDIE RIVERA |
| Insulation | 8/30/2023 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 8/30/2023 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 11/16/2023 | Approved | CHARLES BOGHOSKHAN |
| Shower Pan | 11/16/2023 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Shower Pan | 12/7/2023 | Approved | CHARLES BOGHOSKHAN |
| ELECTRICAL-Final | 1/18/2024 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Final | 1/18/2024 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 1/18/2024 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 2/15/2024 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 2/15/2024 | Approved | FREDDIE RIVERA |
| HVAC-Final | 2/15/2024 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 2/15/2024 | Approved | FREDDIE RIVERA |
| Service/Power Release | 2/15/2024 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 2/22/2024 | Partial Inspection | FREDDIE RIVERA |
| Final | 2/22/2024 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 2/22/2024 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 2/22/2024 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 2/22/2024 | Partial Inspection | FREDDIE RIVERA |
| Final | 6/6/2024 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 6/6/2024 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 6/6/2024 | Partial Inspection | FREDDIE RIVERA |
| Final | 8/30/2024 | Conditional Approval | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 8/30/2024 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 8/30/2024 | Approved | FREDDIE RIVERA |
| Final | 9/9/2024 | Corrections Issued | FREDDIE RIVERA |
| Final | 10/9/2024 | OK to Issue CofO | FREDDIE RIVERA |