13620 W BRANFORD ST 91331
Certificate Information: 13620 W BRANFORD ST 91331
- Application / Permit
- 21016-10000-16932
- Plan Check / Job No.
- B21LA12270
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (E) GARAGE TO BE CONVERTED INTO ADU AS PER GCS65852.2(e)(1)(A) WITH ONE BEDROOM, BATHROOM, LIVING ROOM AND KITCHEN.
- Permit Issued
- Issued on 10/23/2021
- Issuing Office
- Current Status
- CofO Issued on 6/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2021 | CRISTINA SALAZAR |
| Corrections Issued | 7/12/2021 | CRISTINA SALAZAR |
| Plan Check Approved | 8/25/2021 | JOSEPH RAFOLS |
| Issued | 10/23/2021 | APPLICANT |
| Building Plans Picked Up | 11/3/2021 | APPLICANT |
| CofO in Progress | 4/8/2022 | GREGG CUMMINGS |
| CofO Issued | 6/20/2022 | MICHAEL SMITH |
| Permit Finaled | 6/20/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/19/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/19/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2021 | CARLOS AGUILERA |
Contact Information
| No Data Available. |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/10/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 11/10/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 11/10/2021 | Partial Approval | GREGG CUMMINGS |
| Sewer | 11/10/2021 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/17/2021 | No Access for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/17/2021 | No Access for Inspection | GREGG CUMMINGS |
| Green Building Rough | 11/17/2021 | No Access for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 11/17/2021 | No Access for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 11/17/2021 | No Access for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/6/2021 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/6/2021 | No Access for Inspection | GREGG CUMMINGS |
| Green Building Rough | 12/6/2021 | No Access for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 12/6/2021 | No Access for Inspection | GREGG CUMMINGS |
| Underground Mechanical | 12/6/2021 | No Access for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/23/2021 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/23/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 12/23/2021 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 12/23/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 12/23/2021 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/25/2022 | Corrections Issued | GREGG CUMMINGS |
| Underground Mechanical | 1/25/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/27/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 1/27/2022 | Approved | GREGG CUMMINGS |
| Shower Pan | 1/27/2022 | Approved | GREGG CUMMINGS |
| Insulation | 1/31/2022 | Corrections Issued | WILLIAM WREN |
| Insulation | 2/2/2022 | Approved | WILLIAM WREN |
| Drywall Nailing | 2/4/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 2/4/2022 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 3/7/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 3/7/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 3/7/2022 | No Access for Inspection | GREGG CUMMINGS |
| HVAC-Final | 3/7/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 3/7/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/7/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 3/7/2022 | No Access for Inspection | GREGG CUMMINGS |
| Final | 3/15/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 3/15/2022 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/15/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 3/15/2022 | Approved | GREGG CUMMINGS |
| Final | 3/21/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/21/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Final | 3/25/2022 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Final | 3/25/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 3/25/2022 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/25/2022 | SGSOV Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 4/7/2022 | Approved | GREGG CUMMINGS |
| Final | 4/7/2022 | OK to Issue CofO | GREGG CUMMINGS |