4529 W SANTO TOMAS DR 90008

Certificate Information: 4529 W SANTO TOMAS DR 90008

Application / Permit
21016-10000-16767
Plan Check / Job No.
B21LA12149
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan: Soft-Story seismic retrofit per LABC Chapter 93: USING (2) SPECIAL CANTILEVERED COLUMNS WITH GRADE BEAMS.
Permit Issued
Issued on 12/27/2021
Issuing Office
Current Status
CofC Issued on 2/24/2022

Permit Application Status History

Submitted 6/29/2021 APPLICANT
Assigned to Plan Check Engineer 7/28/2021 HANS SANTIAGO
Corrections Issued 8/2/2021 HANS SANTIAGO
Quality Review Completed 8/4/2021 SAI KHUM
Applicant returned to address corrections 10/13/2021 HANS SANTIAGO
Plan Check Approved 11/9/2021 ANDREW SANTIAGO
Issued 12/27/2021 APPLICANT
OK for CofC 2/23/2022 DARRYL ARNOLD
CofC Issued 2/24/2022 WINSTON DUNNING

Permit Application Clearance Information

Tenant Habitability Plan Cleared 12/13/2021 RICARDO BOHORQUEZ

Contact Information

Contractor Titan Contracting Services Inc; Lic. No.: 976552-B 13434 RAYMER STREET      NORTH HOLLYWOOD, CA 91605
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/19/2022 Approved BRUCE CAMPBELL
Footing/Foundation/Slab 2/2/2022 Approved DARRYL ARNOLD
Wood Frame 2/2/2022 Approved DARRYL ARNOLD
Deputy Drilled-In Anchors 2/3/2022 Conditional Approval DARRYL ARNOLD
Deputy Other (see comments) 2/3/2022 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Concrete 2/3/2022 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 2/8/2022 Conditional Approval DARRYL ARNOLD
Final 2/23/2022 OK for CofC DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 2/23/2022 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 2/23/2022 Approved DARRYL ARNOLD