21046-21048 W BALTAR ST 91304

Certificate Information: 21046-21048 W BALTAR ST 91304

Application / Permit
21016-10000-16723
Plan Check / Job No.
B21LA12118
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING 2 CAR ATTACHED GARAGE INTO AN ADU
Permit Issued
Issued on 11/16/2021
Issuing Office
Current Status
CofO Issued on 9/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 FERNANDO FLORES
Corrections Issued 7/9/2021 FERNANDO FLORES
Plan Check Approved 10/5/2021 FERNANDO FLORES
Building Plans Picked Up 10/7/2021 APPLICANT
Issued 11/16/2021 APPLICANT
CofO in Progress 9/12/2022 STEVEN BACK
CofO Issued 9/13/2022 JOHN JANSON
Permit Finaled 9/13/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/27/2021 CARLOS AGUILERA
Sewer availability Cleared 7/27/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/3/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 2919 BURBANK BLVD STE D      BURBANK, CA 91505

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/22/2022 Partial Approval STEVEN BACK
Sewer 2/22/2022 Approved STEVEN BACK
Underground Mechanical 2/22/2022 Partial Approval STEVEN BACK
Footing/Foundation/Slab 3/14/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 4/6/2022 Partial Approval JEFFREY PARD
BUILDING-Rough-Frame 4/27/2022 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 4/27/2022 Approved STEVEN BACK
PLUMBING-Rough 4/27/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 5/16/2022 Approved STEVEN BACK
Insulation 5/16/2022 Approved STEVEN BACK
Interior/Exterior Lathing 5/16/2022 Partial Approval STEVEN BACK
Drywall Nailing 5/23/2022 Corrections Issued STEVEN BACK
Insulation 5/23/2022 Approved STEVEN BACK
Final 7/27/2022 Corrections Issued STEVEN BACK
Green Building Final 7/27/2022 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 7/27/2022 SGSOV Not Ready STEVEN BACK
Smoke Detectors 7/27/2022 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Final 9/6/2022 Approved STEVEN BACK
Final 9/6/2022 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 9/6/2022 SGSOV Approved STEVEN BACK
Service/Power Release 9/6/2022 Not Ready for Inspection STEVEN BACK
Smoke Detectors 9/6/2022 Approved STEVEN BACK
Final 9/12/2022 OK to Issue CofO STEVEN BACK
HVAC-Final 9/12/2022 Approved STEVEN BACK
PLUMBING-Final 9/12/2022 Approved STEVEN BACK