17619 W KITTRIDGE ST 91406

Certificate Information: 17619 W KITTRIDGE ST 91406

Application / Permit
21016-10000-16691
Plan Check / Job No.
B21LA12095
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF (E) 2 CAR GARAGE INTO ADU PER GCS65852.2(e)(1)(A)
Permit Issued
Issued on 1/5/2022
Issuing Office
Current Status
CofO Issued on 4/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 RICARDO RAMIREZ
Corrections Issued 7/9/2021 RICARDO RAMIREZ
Applicant returned to address corrections 10/15/2021 RACHEL BEYENE
Applicant returned to address corrections 11/4/2021 SINA KHOSRAVI
Applicant returned to address corrections 11/17/2021 TSE MING HUANG
Plan Check Approved 11/29/2021 TSE MING HUANG
Building Plans Picked Up 12/1/2021 APPLICANT
Issued 1/5/2022 APPLICANT
CofO in Progress 3/22/2024 JON MCHUGH
CofO Issued 4/12/2024 JOHN JANSON
Permit Finaled 4/12/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/15/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/15/2021 CARLOS AGUILERA
Sewer availability Cleared 7/15/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 9/13/2021 ROBERT DUFF

Contact Information

Contractor Refinish Plus Inc; Lic. No.: 1050293-B 8133 PURITAN ST      DOWNEY, CA 90242

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/21/2022 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 1/21/2022 Partial Approval SEAN HAUPT
Deputy Drilled-In Anchors 2/11/2022 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 2/11/2022 Approved SEAN HAUPT
Underground Mechanical 2/17/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 3/25/2022 Not Ready for Inspection SEAN HAUPT
Deputy Drilled-In Anchors 3/25/2022 Conditional Approval JUSTIN HAWLEY
ELECTRICAL-Rough 3/25/2022 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 3/25/2022 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 3/25/2022 Approved SEAN HAUPT
Wood Frame 3/25/2022 Approved SEAN HAUPT
Green Building Rough 4/5/2022 Approved SEAN HAUPT
Rough-Elec/Plmb/HVAC 4/5/2022 Approved SEAN HAUPT
Wood Frame 4/5/2022 Approved SEAN HAUPT
Insulation 4/11/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 4/11/2022 Approved SEAN HAUPT
Drywall Nailing 4/20/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 5/2/2022 Approved SEAN HAUPT
Shower Pan 5/2/2022 Approved SEAN HAUPT
Service/Power Release 9/19/2023 Corrections Issued JON MCHUGH
BUILDING-Rough-Frame 11/16/2023 Approved JON MCHUGH
Final 11/16/2023 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 11/16/2023 SGSOV Approved JON MCHUGH
Service/Power Release 11/16/2023 Not Ready for Inspection JON MCHUGH
Smoke Detectors 11/16/2023 Approved JON MCHUGH
ELECTRICAL-Final 3/11/2024 Not Ready for Inspection JON MCHUGH
Final 3/11/2024 Corrections Issued JON MCHUGH
Green Building Final 3/11/2024 Approved JON MCHUGH
HVAC-Final 3/11/2024 Not Ready for Inspection JON MCHUGH
PLUMBING-Final 3/11/2024 Approved JON MCHUGH
ELECTRICAL-Final 3/22/2024 Approved JON MCHUGH
Final 3/22/2024 OK to Issue CofO JON MCHUGH
Green Building Final 3/22/2024 Approved JON MCHUGH
HVAC-Final 3/22/2024 Approved JON MCHUGH
PLUMBING-Final 3/22/2024 Approved JON MCHUGH
Service/Power Release 3/22/2024 Approved JON MCHUGH