6314 W DE LONGPRE AVE 90028
Certificate Information: 6314 W DE LONGPRE AVE 90028
- Application / Permit
- 21016-10000-16675
- Plan Check / Job No.
- B21LA12080
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Fence Wall
- Work Description
- ADDITION OF STEEL FENCES AND GATES AT SELECT LOCATIONS ON PERIMETER OF MIXED USE COMMERCIAL AND RESIDENTIAL PROJECT. REF. ZA-2015-1766-MCUP-VCU-SPR-PA1.
- Permit Issued
- Issued on 9/8/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 3/20/2023
Permit Application Status History
| Submitted | 7/8/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 7/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | LAMAR DAVIS |
| Corrections Issued | 8/3/2021 | LAMAR DAVIS |
| Quality Review Completed | 8/11/2021 | KEN GILL |
| Building Plans Picked Up | 8/13/2021 | APPLICANT |
| Plan Check Approved | 9/7/2022 | LAMAR DAVIS |
| Issued | 9/8/2022 | APPLICANT |
| Permit Finaled | 3/17/2023 | RONALD JIMENEZ |
Permit Application Clearance Information
| Green Code | Cleared | 7/30/2021 | NEGAR NEJAD |
| Historic Resource Verification | Cleared | 8/17/2021 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 8/25/2021 | DAVID URITA |
| ZI | Cleared | 8/30/2021 | JIVAR AFSHAR |
| DAS Clearance | Cleared | 8/24/2022 | CHOI YAN |
| "D" conditions | Cleared | 9/2/2022 | ANACANY HURTADO |
| Miscellaneous | Cleared | 9/2/2022 | ANACANY HURTADO |
| ZA Case | Cleared | 9/2/2022 | ANACANY HURTADO |
| ZA Case | Cleared | 9/7/2022 | ANACANY HURTADO |
Contact Information
| Architect | House,, James Douglas; Lic. No.: C15526 | 10125 WASHINGTON BLVD CULVER CITY, CA 90232 |
| Contractor | Hathaway Dinwiddie Construction Company; Lic. No.: 729664-B | 275 BATTERY STREET SUITE 300 SAN FRANCISCO, CA 941113330 |
| Engineer | Chamberlain,, Craig Morgan; Lic. No.: S4588 | 1517 23RD ST MANHATTAN BEACH, CA 90266 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/28/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Structural Steel Frame | 10/11/2022 | Partial Approval | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 10/18/2022 | Partial Approval | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 11/2/2022 | Partial Approval | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 11/4/2022 | Partial Approval | TIMOTHY BUXTON |
| Excavation/Setback/Form/Re-Bar | 12/20/2022 | Partial Approval | ALAN MORELOS |
| Final | 3/17/2023 | Permit Finaled | RONALD JIMENEZ |