1644 1/2 S BERENDO ST 90006
Certificate Information: 1644 1/2 S BERENDO ST 90006
- Application / Permit
- 21016-10000-16657
- Plan Check / Job No.
- B21LA12065
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT ONE-CAR GARAGE AND PLAYROOM TO ADU PER GCS 65852.2(e)(1)(A) . TWO BEDROOMS, ONE BATHROOM, LIVINGROOM AND KITCHEN 498 SQ.FT.
- Permit Issued
- Issued on 9/20/2021
- Issuing Office
- Current Status
- CofO Issued on 4/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | RACHEL BEYENE |
| Corrections Issued | 7/9/2021 | RACHEL BEYENE |
| Applicant returned to address corrections | 8/19/2021 | JESSE JIMENEZ |
| Plan Check Approved | 9/3/2021 | DANIEL SANJUAN |
| Issued | 9/20/2021 | APPLICANT |
| Building Plans Picked Up | 9/23/2021 | APPLICANT |
| CofO in Progress | 4/19/2022 | KATHRYN BUTTERWORTH |
| Permit Finaled | 4/28/2022 | DEROLD HAUFF |
| CofO Issued | 4/28/2022 | DEROLD HAUFF |
| Permit Finaled | 4/28/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2021 | CECILIO NAVARRO |
| Address approval | Cleared | 8/3/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 8/3/2021 | CECILIO NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/12/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Footing/Foundation/Slab | 10/12/2021 | Corrections Issued | ROBERT VORHIS |
| Pre-Inspection | 10/27/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 11/16/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 11/23/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 11/23/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 11/23/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Sewer | 11/23/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 11/30/2021 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 12/3/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Sewer | 12/3/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Sewer | 12/7/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 12/8/2021 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 12/13/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 12/13/2021 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 12/13/2021 | Approved | KATHRYN BUTTERWORTH |
| Sewer | 12/16/2021 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 12/22/2021 | Partial Inspection | AMY COLIN |
| Wood Frame | 1/5/2022 | Approved | SHAVONNE ESPINOZA |
| Insulation | 1/6/2022 | Corrections Issued | JOSE AVILA |
| Drywall Nailing | 1/10/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 1/10/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 1/12/2022 | Conditional Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 1/25/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 1/25/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 1/25/2022 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 1/25/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Shower Pan | 2/1/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Underground Mechanical | 2/1/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Gas Test | 2/14/2022 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 2/14/2022 | Approved | KATHRYN BUTTERWORTH |
| Shower Pan | 2/14/2022 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 2/28/2022 | Approved | KATHRYN BUTTERWORTH |
| Final | 2/28/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 2/28/2022 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 2/28/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 3/2/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 3/2/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| HVAC-Final | 3/2/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 3/2/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Service/Power Release | 3/2/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 3/4/2022 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 3/17/2022 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 3/23/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 3/23/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| HVAC-Final | 3/23/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 3/23/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 3/23/2022 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Service/Power Release | 3/23/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Smoke Detectors | 3/23/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 3/31/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 3/31/2022 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Service/Power Release | 3/31/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Smoke Detectors | 3/31/2022 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 4/4/2022 | Approved | SCOTT FINNILA |
| HVAC-Final | 4/4/2022 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 4/4/2022 | Approved | SCOTT FINNILA |
| Final | 4/13/2022 | OK to Issue CofO | KATHRYN BUTTERWORTH |
| Service/Power Release | 4/13/2022 | Approved | KATHRYN BUTTERWORTH |