1053 1/2 S RIMPAU BLVD 90019
Certificate Information: 1053 1/2 S RIMPAU BLVD 90019
- Application / Permit
- 21016-10000-16318
- Plan Check / Job No.
- B21LA11870
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE /LAUNDRY (499 SF ZONING) INTO ADU PER LAMC 12.22 A.33 (c)-(d); ALL WORKS PER ENGINEER DESIGN
- Permit Issued
- Issued on 10/6/2021
- Issuing Office
- Current Status
- CofO Issued on 3/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2021 | SINA KHOSRAVI |
| Corrections Issued | 7/4/2021 | SINA KHOSRAVI |
| Applicant returned to address corrections | 9/1/2021 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 9/18/2021 | AUNG SOE |
| Plan Check Approved | 9/20/2021 | AUNG SOE |
| Issued | 10/6/2021 | APPLICANT |
| Building Plans Picked Up | 10/8/2021 | APPLICANT |
| CofO in Progress | 3/7/2022 | ARTHUR SARGSYAN |
| Permit Finaled | 3/2/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/2/2023 | DANIEL ORRANTE |
| CofO Issued | 3/2/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| CPC | Cleared | 7/19/2021 | JOE LUCKEY |
| Sewer availability | Cleared | 7/20/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2021 | THOMAS LANG |
| Construction near power lines | Cleared | 8/21/2021 | RIDWAN HARDY |
| Tenant Habitability Plan | Cleared | 8/24/2021 | ISMAEL HERNANDEZ |
| Address approval | Cleared | 9/4/2021 | THOMAS LANG |
Contact Information
| Contractor | Rebuilt; Lic. No.: 1063540-B | 2201 N LAKEWOOD BLVD STE D643 LONG BEACH, CA 90815 |
| Engineer | Gonzalez,, Felix Bolivar; Lic. No.: C64738 | 14619 CATALINA AVE GARDENA, CA 90247 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/25/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 10/25/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 10/25/2021 | Approved | ARTHUR SARGSYAN |
| METHANE-Rough | 10/25/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 10/25/2021 | Approved | ARTHUR SARGSYAN |
| Insulation | 10/29/2021 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 11/9/2021 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 11/22/2021 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 12/9/2021 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 12/14/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 2/15/2022 | Approved | ARTHUR SARGSYAN |
| Final | 2/15/2022 | Not Ready for Inspection | ARTHUR SARGSYAN |
| HVAC-Final | 2/15/2022 | Corrections Issued | ARTHUR SARGSYAN |
| PLUMBING-Final | 2/15/2022 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 2/15/2022 | SGSOV Approved | ARTHUR SARGSYAN |
| Service/Power Release | 2/15/2022 | Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 2/15/2022 | Not Ready for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 3/1/2022 | Approved | ARTHUR SARGSYAN |
| Final | 3/1/2022 | OK to Issue CofO | ARTHUR SARGSYAN |
| HVAC-Final | 3/1/2022 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Final | 3/1/2022 | Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 3/1/2022 | Approved | ARTHUR SARGSYAN |