668-668 1/2 W 28TH ST 90007
Certificate Information: 668-668 1/2 W 28TH ST 90007
- Application / Permit
- 21016-10000-16314
- Plan Check / Job No.
- B21LA11865
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EXTERIOR REMODEL AND CONVERT (E) PARKING AREA UNDER (E) 2-STORY APARTMENT TO 1-STORY ATTACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(C)
- Permit Issued
- Issued on 12/28/2021
- Issuing Office
- Current Status
- CofO Issued on 1/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | DANIEL YIP |
| Corrections Issued | 7/20/2021 | DANIEL YIP |
| Quality Review Completed | 7/26/2021 | JASON HEALEY |
| Building Plans Picked Up | 7/29/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 8/10/2021 | APPLICANT |
| Applicant returned to address corrections | 8/26/2021 | DANIEL YIP |
| Applicant returned to address corrections | 10/22/2021 | DANIEL YIP |
| Plan Check Approved | 12/14/2021 | DANIEL YIP |
| Issued | 12/28/2021 | APPLICANT |
| TCO Issued (Expire Date: 05-03-2023) | 11/4/2022 | TED RIES |
| CofO in Progress | 1/13/2023 | ERNESTO CORRAL |
| CofO Issued | 1/13/2023 | ERNESTO CORRAL |
| Permit Finaled | 1/13/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Redevelopment Project Area | Cleared | 8/13/2021 | GRACIELA ACOSTA |
| Address approval | Cleared | 8/17/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 8/20/2021 | CECILIO NAVARRO |
| ZI | Cleared | 8/20/2021 | JOE LUCKEY |
| Roof/Waste drainage to street | Cleared | 9/14/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 9/15/2021 | MATTHEW CRAIG |
| Frnt yard landscape/Water mgmt | Cleared | 10/4/2021 | JASON CHAN |
| DAS Clearance | Cleared | 10/7/2021 | DANIEL YIP |
Contact Information
| Architect | Gevorkyan,, Sona; Lic. No.: C37020 | 2823 ALLESANDRO STREET LOS ANGELES, CA 90039 |
| Contractor | Dh Remodel Services; Lic. No.: 1030925-B | 5850 W 3RD STREET #160 LOS ANGELES, CA 90036 |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/28/2022 | Approved | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 2/16/2022 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| METHANE-Barrier | 2/16/2022 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| METHANE-Subgrade | 2/16/2022 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 2/22/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Green Building Rough | 2/22/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| METHANE-Rough | 2/22/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| METHANE-Rough | 3/4/2022 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| METHANE-Subgrade | 3/4/2022 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| METHANE-Rough | 3/11/2022 | Approved | RUSSELL BONVOULOIR |
| Pre-Inspection | 3/14/2022 | Approved | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 3/17/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Pre-Inspection | 3/17/2022 | Approved | RUSSELL BONVOULOIR |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Green Building Rough | 3/23/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Pre-Inspection | 3/23/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Wood Frame | 3/23/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Green Building Rough | 4/11/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Wood Frame | 4/11/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Insulation | 4/14/2022 | Approved | RUSSELL BONVOULOIR |
| Interior/Exterior Lathing | 4/14/2022 | Approved | RUSSELL BONVOULOIR |
| Green Building Rough | 4/15/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Pre-Inspection | 4/15/2022 | Approved | RUSSELL BONVOULOIR |
| Special/Order Compliance | 4/15/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Wood Frame | 4/15/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Drywall Nailing | 4/18/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Pre-Inspection | 4/18/2022 | Approved | RUSSELL BONVOULOIR |
| Green Building Rough | 4/22/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Wood Frame | 4/22/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Interior/Exterior Lathing | 4/29/2022 | Approved | RUSSELL BONVOULOIR |
| Pre-Inspection | 4/29/2022 | Approved | RUSSELL BONVOULOIR |
| Drywall Nailing | 5/11/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Green Building Rough | 5/11/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Pre-Inspection | 5/11/2022 | Approved | RUSSELL BONVOULOIR |
| Pre-Inspection | 6/7/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Drywall Nailing | 8/15/2022 | Approved | RUSSELL BONVOULOIR |
| Final | 8/15/2022 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 8/15/2022 | Approved | RUSSELL BONVOULOIR |
| Green Building Final | 8/15/2022 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Green Building Rough | 8/15/2022 | Approved | RUSSELL BONVOULOIR |
| METHANE-Barrier | 8/15/2022 | Approved | RUSSELL BONVOULOIR |
| METHANE-Subgrade | 8/15/2022 | Approved | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 8/15/2022 | SGSOV Not Ready | RUSSELL BONVOULOIR |
| Smoke Detectors | 8/15/2022 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Structural Steel Frame | 8/15/2022 | Approved | RUSSELL BONVOULOIR |
| Wood Frame | 8/15/2022 | Approved | RUSSELL BONVOULOIR |
| Final | 8/18/2022 | Off-Hour Fees Due | |
| Green Building Final | 8/18/2022 | Off-Hour Fees Due | |
| SGSOV-Seismic Gas S/O Valve | 8/18/2022 | Off-Hour Fees Due | |
| Smoke Detectors | 8/18/2022 | Off-Hour Fees Due | |
| Final | 11/16/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Green Building Final | 11/16/2022 | Approved | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 11/16/2022 | SGSOV Approved | RUSSELL BONVOULOIR |
| Smoke Detectors | 11/16/2022 | Approved | RUSSELL BONVOULOIR |